Print Proposal Graphics:
MASTER PLAN FOR THE EAST LAKE MARTA STATION AREA
2017
19
JULY
26
3
10
17
AUGUST
24
31
7
14
21
2018
SEPTEMBER
28
4
11
18
OCTOBER
25
2
9
16
NOVEMBER
23
30
6
13
20
DECEMBER
27
4
11
JANUARY
18 25
JUNE
12
Proposed Schedule: June 2017 - February 2018
1
8
15
FEBRUARY
22
29
5
12
19
26
Phase 1: Existing Conditions and Market Assessment
May 2017
Project Management Team Meeting #1
Site Visit and Photo Inventory/Reconnaissance Survey
Review Existing Plans and Relevant Resources
Develop Existing Conditions Assessment Report
Prepare Preliminary Findings Briefing and Refined Project Approach
Project Management Team Meeting #2
Review Existing Market Conditions
Conduct Market Assessment and Prepare Initial Findings
Stakeholder Committee Meeting #1
Phase 2: Vision and G