Cold Link Africa November / December 2019 | Page 37

CONTRIBUTORS INCORPORATING COLD CHAIN attention if not done by the contractor 7 . See also comments under the subheading guarantees and security above. There appears to be a degree of conflict between the provisions of clause 38.5.4 on the one hand which, by reference to clause 34.0, places the final account within the ambit of the normal relationship between contractor and subcontractor, and clauses 38.5.5 and 38.5.7 which provide for payment by the employer to the subcontractor. The following thoughts are submitted to deal with the provisions of these clauses: 1. The challenge of excluding the contractor is that there may be matters as between the contractor and the subcontractor that need to be dealt with by the contractor and in which the employer does not wish to and should never become involved. The continuation of the construction and payment guarantees up to the issue and payment of the final payment advice would generally cover any adjustments that may occur after the last payment advice statement issued prior to termination. 2. The principal building agreement at clause 36.0 Termination by employer – contractor’s default provides that the contractor is entitled only to nil interim payment certificates until after the final payment certificate is issued. This would mean that by reference to the provisions of clause 31 8 , the subcontractor would similarly not be entitled to any payments until the issue of the final payment certificate and an employer wishing to retain a n/s subcontractor’s services to complete the work would find itself at a disadvantage by not being contractually entitled to make good at least the uncertified part of the unpaid balance due to the subcontractor, particularly where liquidation supervenes. 3. PBA clause 38.0 Termination by contractor – employer’s default provides for ongoing interim payments to the contractor similarly to NSSA clause 38.0 and therefore there would be no problem with payments in the (unlikely) event the employer does pay. However, the subcontractor could be prejudiced by issues between the contractor and the employer that result in non- certification or non-payment to the contractor. 4. Therefore, the n/s final account for work completed prior to termination should be processed through the contractor and in terms of all the provisions of and referred to in clause 34.0 with all its sub-clauses, which include inter alia sub- clause 34.7 providing for amounts recoverable by the employer in terms of a recovery statement. A subcontractor when dealing with an insolvent contractor will probably only be entitled to recover payments Subcontractors must understand what the law says and its relevance to the contract established. certified and paid by the employer prior to termination in terms of the distribution account from the insolvent estate 9 . This may be a very good reason for the exercise of any liens or other defences and the removal from site of any unpaid goods 10 . 5. The subcontractor can and should immediately exercise a lien and/or reservation of ownership over unpaid materials and goods, even to the point of including identifiable and detachable and removable elements which have been placed/fixed but can be easily removed, in the lien 11 . 6. The difficulty of providing for defects or overpayments to the subcontractor before termination is a matter that could be adjusted if the subcontractor is appointed to complete the n/s works. However, when the subcontractor is not available to continue after termination or where the employer prefers to employ a new subcontractor, it could but should not create a challenge for the employer if it pays directly and then tries to deduct any sum for defective or overpaid work from the contractor’s final account, notwithstanding that 7. The subcontractor should receive a payment notification from the principal agent when any certificate including a final payment certificate is issued but there is no obligation on the principal agent to notify the subcontractor when any of the various completion certificates are issued. Equally, there is nothing that prevents the principal agent from copying all n/s subcontractors in on any electronic issue of such completion certificates and the subcontractor should make written request that this be done after the termination of the contractor. 8. Inter alia sub-clause 31.5.1 9. Hence the need for clause 38.5.5 and 38.5.7 providing for direct payment to the subcontractor as discussed under those provisions. 10. See inter alia Concor Holdings (Pty) Ltd v Potgieter (219/03), [2004] ZASCA (28 May 2004); Administrator General South West Africa v Trust Bank of Africa Ltd 1982 (1) SA 635 (SWA) 11. Legal opinion should be sought if the lien is disputed and a discussion on liens falls outside the scope of this paragraph. Suffice it to point out that the principles accessio inaedificatio (ownership through attachment of goods to immobile property) do not fully preclude the availability of a lien on easily identifiable isolated and detachable goods (see inter alia Melcorp SA (Pty) Ltd v Joint Municipal Pension Fund (Transvaal) 1980 2 SA 214 (W). COLD LINK AFRICA • November/December 2019 www.coldlinkafrica.co.za 37