Cold Link Africa November / December 2019 | Page 38

CONTRIBUTORS INCORPORATING COLD CHAIN Payment agreements/clauses need to be clearly stipulated even after the contract is cancelled. the contractor remains the party that is liable to the employer for defects in any part of the works including any n/s works 12 . A direct payment for unpaid materials and goods (and completed n/s work) should at the very least be very specific as to what is being paid for and the amount thereof as well as the specific terms on which it is made so that the possibility for a later vindicatory action by the employer against the subcontractor is at least possible 13 on the basis of records. 7. It is therefore submitted that aside from a reconciliation of the amount due to the subcontractor for materials and goods on site and payment of any outstanding balance directly to the subcontractor, the settlement of the amount due on the n/s final account would have to be through the office of the principal contractor and in terms of clause 34.0 which would, for those purposes, be deemed to survive the termination as suggested by the wording of clause 38.5.4. 8. NSSA clause 34.5 very specifically provides that except for terminations in terms of clauses 36 14 (subcontractor’s default) and 39 (vis major), the issue of the final completion certificate is a pre- requisite for the issue of the final payment certificate. Therefore, whilst the subcontractor is entitled to interim payment of amounts for work and materials not certified by the date of termination, the subcontractor will not be entitled to a final payment advice before the final payment certificate is issued to the contractor. This potentially impinges the available security between the contractor and subcontractor. 9. The principal agent should compile and issue a final account for the n/s works as completed at date of termination including materials and goods payable in terms of clause 38.5.5 and 38.5.7, reflecting the full amount due to the subcontractor and adjust for 12. direct payments in terms of clause 38.5.5 and 38.5.7 by way of a recovery statement item. Sadly, the principal building agreement at clause 33.2.8, whilst providing for direct payments in terms of clauses 20.6 (failure to pay nominated subcontractors) and 21.6 (failure to pay selected subcontractors) does not include a specific provision for recovery of direct payments in terms of NSSA clause 38.5. The conclusion can be made that the direct payments resort under PBA clause 33.2.6 (… expense and loss … resulting from … the agreement being terminated [36.0]) thereby defining the need to make direct payment as a prejudice incurred by the employer as a result of terms stipulated for in the termination provisions of the subcontract which practically result in privity of contract between employer and subcontractor because the subcontractor acquires a direct entitlement to payment. This would probably be the preferable route when insolvency supervenes as the liquidator is only entitled to such funds as may become available for the completed project after deduction of all costs of bringing the works to completion. 10. Any direct payment of certified amounts in terms of PBA clauses 20.6/21.6 based on certificates issued prior to termination but after insolvency has supervened would probably be capable of challenge by the liquidator 15 and should be carefully considered. This does not preclude the subcontractor from adding them as an effective premium claimed by the subcontractor within its price for completion of the n/s works thereby effectively rendering it an expense and loss to the employer in terms of PBA clause 33.2.6. *Note: this is not a legal opinion and no liability for reliance on its contents attaches to the writer or sender. CLA See Minister of Public Works and Land Affairs v Group Five Building Ltd 1999 (4) SA 12 (AD) 13. Reliance on common law actions such as the actio quanti minoris, condictio indebiti and the like is subject to very strict application and there is no better than a mutually agreed process and grounds for correction of an overpayment. 14. It is submitted that there is an error in this clause, and it should read 38 rather than 36. 15. See Administrator, Natal v Magill, Grant & Nell (Pty) Ltd (in Liquidation) 1969 (1) SA 660 (A) 671H-672B. 38 www.coldlinkafrica.co.za COLD LINK AFRICA • November/December 2019