Cold Link Africa November / December 2019 | Page 36

CONTRIBUTORS INCORPORATING COLD CHAIN This status report must be very detailed ability to use completed n/s works, as it may serve as evidence for: all of which will acquire significance if the contractor attempts to raise penalties and ‘contra-charges’ in the final payment advice it issues. 1. the subcontractor’s claim against the contractor for work completed where there is any dispute on amounts certified to and payable by the contractor in terms of all elements of the payment advice and recovery statements 6 ; 2. definition of the work to be carried out after termination for the employers account which in turn could serve as a basis for proving its damages; 3. a basis for establishing the amount the employer will have to pay the subcontractor to complete the n/s works (a subcontractor may think it disadvantageous to make all this information available but proper records are an important aid in litigation); 4. evidence of the subcontractor’s ability to execute n/s works which are dependent on the contractor’s prior completion of precedent activities as well as the contractor’s 6. The subcontractor should start working on it as early as possible if it becomes aware of the intended termination. It is not just the normal progress report that can be compiled by the site team as part of their normal routine. Clause 38.5.4 The principal agent shall timeously commence and complete the n/s final account [34.0]. The same comment as above applies with regards to the subcontractor taking the initiative. The final account so prepared is essentially concerned with work completed up to the date of termination inclusive of any additional sums which become payable in terms of clauses 38.5.5 and 38.5.7. The reference to clause 34.0 appears to incorporate its provisions regarding agreement and settlement of the final account and the issue of the final payment advice. However, given the termination of the principal contract, the contractor is no longer involved and the relevance and application of some of the sub-clauses of clause 34.0 could become arguable. Both the payment and the construction guarantees are applicable as between contractor and subcontractor and the employer has no role to play other than to ensure the issue of completion certificates is brought to the terminated contractor’s and the subcontractors’ It is important to understand your position, roles and responsibilities as a contractor when drafting a contract. It is submitted that the contractor and the subcontractor involved, are liable for the costs of making good any defects in the n/s works for which payment has been made i.e. the employer does not acquire liability for the costs incurred by the new n/s subcontractor in making good defective work completed and paid for prior to termination even when certified by a specialist agent. Such costs become part of the employer’s damages claim against the contractor who in turn would have a right of recovery against the subcontractor (see Minister of Public Works and Land Affairs v Group Five Building Ltd 1999 (4) SA 12 (AD) and dicta about the principal agent’s obligations in Strijdom Park Extension 6 (Pty) Ltd v Abcon (Pty) Ltd 1998 (4) SA 844 (SCA)). This is particularly important in sophisticated specialist trades such as electronics and HVAC. There could be a defense to such a claim in terms of NSSA clause 38.5.9 (termination of latent defects liability period) but it would probably be tenuous. The matter is discussed at bullet 9 hereunder. Therefore, the position seems to be that damages are recoverable for defective work that is discovered prior to settlement of the final account but only to the extent it does not qualify as a latent defect. It is evident that this somewhat confusing situation could result in litigation. 36 www.coldlinkafrica.co.za COLD LINK AFRICA • November/December 2019