• COUNTRY IN FOCUS
keeping the talc material away from the critical main drains. He pointed out that, as part of the application of best practice, the TSF was not only clay-lined but there was also extensive use of highdensity polyethylene lining in the drains.
“ Within the footprint of the dam itself, all the drains are lined with HDPE as well,” said McNeill.“ Using both the clay lining – including a four-metre layer of clay on the walls – and the HDPE represented quite a unique approach. This was the optimal response to both the geochemistry and the very flat gradients at the site.”
Green wall Another innovation was the application of the‘ rising green wall’ concept – in which the outside wall of the TSF is progressively vegetated as the facility grows in height. As each bench is raised to accommodate the continued discharge of tailings, a layer of topsoil is applied and vegetation is cultivated.
“ This is a positive advance from the traditional practice, when operators would wait until the TSF was at its full height and at the end of its operating life before starting to rehabilitate the outside of the walls,” said Robertshaw..“ An advantage of this strategy is that dust is reduced, and the cost of vegetating the TSF is spread over the life of the facility – rather than demanding all this expenditure at once at the end of its active life.”
By facilitating the rising green wall, SRK’ s design also aligned with best practice in TSF closure – which favours progressive and ongoing rehabilitation during the life-of-mine, so that the practical and financial demands are not concentrated very late in the mining life-cycle.
“ To allow vegetation the best chance to take root on a TSF, the design should avoid long slopes that are susceptible to erosion from rainfall run-off,” he said.
Prioritising empowerment At the heart of this project was a close working relationship with the client that prioritised the engagement and empowerment of Zimbabwean firms, highlighted Robertshaw. With its focus on quality standards across the project, SRK Consulting( SA) provided technical guidance for local company Kumba Resources Zimbabwe to set up an on-site laboratory.
“ This testing facility was important for taking samples of various materials and delivering quick results – which streamlined the pace of the project,” he said.“ Testing earthworks materials and concrete, and keeping detailed records over the length of the project, was a key component of quality assurance on the site.”
The Kumba laboratory team numbered almost a dozen, including specialist samplers and testing technicians. Towards the end of the project, they worked around the clock in three shifts to complete the necessary work in time. Robertshaw commended the dedication and expertise of the laboratory team, which has now developed a strong track record of providing on-site quality assurance to a large TSF development. Kumba has established a new laboratory in Harare following the project, building on their foundation of extended mentoring on the Mimosa site.
Supporting local contractor A similar developmental approach was taken with the role of Forit Contracting – the main earthworks contractor. SRK Consulting( SA) worked with the mine and the contractor to ensure the necessary resources were available and fully utilised. The early site clearing was undertaken manually, but as the project gathered momentum, Forit was able to increase its earthmoving plant fleet on site to around 150 items at the peak.
Tasked by the client to provide a safety officer on site, SRK Consulting( SA) appointed a local safety officer and raised his skill level through training to achieve an international safety qualification. Among the critical safety factors was the capability of working at heights on the 40 m penstock towers, which required the relevant expertise and experience. Training in working at heights was therefore conducted for a number of the workers on the project.
Designed for the long run Future-proofing has also been an important element of the TSF design, he pointed out, as the first brief was for a TSF height of only 30 metres.
The HDPE represented quite a unique approach. This was the optimal response to both the geochemistry and the very flat gradients at the site.
View from TSF3 north along western flank of TSF4. Visible are the outer paddocks, the Starter Wall, clay lining under Toe Drain and excavation for Main Drain One and Main Drain two.