COUNTRY IN FOCUS •
View of TSF4 from Northwest showing the northern return water pumpstation, the internal paddock arrangement, the Starter Wall with Toe drain, Main Drain One and Main Drain Two.
All images supplied by SRK Consulting

MIMOSA TSF SHOWCASES RESPONSIBLE MINING IN ZIMBABWE

Contributed by SRK Consulting
Extending the tailings storage facility( TSF) at Zimbabwe’ s Mimosa platinum mine has involved the construction of a new dam, based on a design which addressed a range of interesting challenges.

The new facility – TSF4 – was designed by SRK Consulting( South Africa), who also managed the two-year construction phase which was completed in March 2024. Leading the SRK team was partner and principal civil engineer Andrew Robertshaw, who pointed out several unusual aspects of the project that required an innovative approach.

“ The existing TSF at Mimosa had experienced challenges related to a fine talc in the discharged tailings, which would settle and impede the crucial function of the TSF drainage system,” said Robertshaw.“ This would lead to standing pools of water above the drains, as the fines would clog the outlets and prevent effective drainage.”
SRK corporate consultant Robert McNeill emphasised that the drainage system had to be specially designed to deal with the challenge of the talc content. The nature of the talc was that it would ultimately settle as soon as the tailings slurry stopped moving. In response, SRK’ s design provided for a comprehensive drainage network while also significantly increasing the drains’ cross-sectional area allowing for deposition of talc to take place quickly towards the centre of the TSF – so that it would not settle on the drains.
Focus on deposition“ The drains themselves were similar to the many other TSF projects we have conducted, but what made this unique was the design that allowed the tailings to be deposited in a particular way,” said McNeill.
SRK partner and principal civil engineer Andy Robertshaw.
SRK Consulting( SA) corporate consultant Rob McNeil.
Of the two sets of drains designed into the TSF, the one that will serve the facility at its full height of 60 metres would not normally be covered by coarse tailings early on – but needs to remain unblocked for an extended period.
“ For the other drain – which is 80 metres from the edge of the TSF – we created a series of secondary paddocks to force the flow of tailings at the required discharge volumes,” Robertshaw explained.“ The overspill from the paddocks keeps up the energy of the flow, so that the talc remains in suspension in the tailings and is taken away from the outside edge. This outside edge is the critical area of the TSF – allowing for stability and drainage.”
Clay and HDPE lining The paddocks were an important element of McNeill’ s commissioning plan, which allows early deposition of tailings while