PROJECT UPDATES – BOTSWANA
Sesigo Mews
fills the gap
for upmarket
residential
apartments
By Onkgopotse Funkie Moroka
Time Projects is bringing another residential development to Gaborone
situated at Plot 75068 in Block 5. This development has 41 apartments
in 5 blocks consisting of 27 X 2-bedroom flats, 13 X 1-bedroom flats
and 1 X 3-bedroom flat. The contractor has already been handed the
site and ground breaking is expected to take place mid-September
with expected completion by July 2020. With close to 90% offers
signed, the sales of the apartments are moving quickly. With only a few
apartments remaining you can still be part of this upcoming development
right in the vicinity of the city centre.
Safety first at SPAR’s specialist facility
By Mmika Selei
With only three and half months left before handover of this specialist facility,
the project has progressed well to date. All the major sub-contractors have
been appointed. We have just finished the erection of the structural steelwork,
with columns going as high as 20m to the first half of the building. All has
been approved and the roof sheeting will be commencing shortly. Major
procurement for the wet and fire services equipment has been concluded with
deliveries expected from the first week of September. We are currently co-
12
ordinating the work to be done by specialist contractors which includes a cold
room, refrigeration room, bakery and concrete floor installations.
What is really commendable is that we have not had a safety incident,
even though we had people working at extreme heights. This goes
to show that we take safety seriously and it is enforced upon all team
members who work on our developments.