County Distance Description
Pleasants 8.88 miles Resurfacing and repairing drainage, ditches and shoulders on Schulz Road and Federal Ridge Pocahontas 30.74 miles
Resurfacing Beverage Road – Clover Lick, Cass Durbin and Greenbank, Sheets and Hill Country roads
Preston
7.02 miles
Paving and repairing ditches and guardrails on Hazelton – Maryland, Greens Run and
Manheim Road
Putnam
18.39 miles
Widening I-64 to six lanes and building a new bridge across the Kanawha River at the U. S.
Route 35 / I-64 Interchange at Nitro
Randolph 15.98 miles
Resurfacing Chenoweth Creek – Kelly Mountain, Roaring Creek Structure and Georgetown and Country Club roads and replacing the 20-foot span with a 40-foot bridge with detour on the Cravensdale Bridge
Ritchie 6.41 miles Resurfacing and repairing drainage and guardrails on Cairo-Cisco Road
Roane
14.88 miles
Resurfacing and repairing drainage, ditches and shoulders on Johnson Creek, Vandale Fork
and Linden and Speed roads
Summers
5.43 miles
Paving and repairing embankment, slide damage and shoulders on Mead Creek and Indian
Ridge roads
Taylor
5.37 miles
Paving and repairing slip damage, culverts and guardrails on Corbin Branch Road and
Old 50 East
Tucker 8.38 miles Resurfacing Cortland and Shavers Fork roads Upshur 13.27 miles Replacing culverts on Corridor H
Webster
10.42 miles
Resurfacing, widening and repairing drainage and guardrails on Replete Road and the
Bergoo Road arch
Wood
12.03 miles
Resurfacing, rehabilitating roadway with slab replacements and repairing drainage, ditches
and shoulders on Spider Ridge, Love Hill, Pond Creek and Community Acres
Wyoming
48.33 miles
Widening road and repairing shoulders on Campus Logan Road and Pineville and
rehabilitating the Ken Shadrick Bridge