Sum of Labor Hours |
Debris Hauled |
|
( in cubic yards ) |
||
Backfill |
83.5 |
5 |
Bridge Deficiency Repair |
179 |
44 |
Clean Concrete Channel |
2851.75 |
166 |
Clean Culvert / Bridge |
1640 |
159 |
Clean Earthen Channel |
406 |
15 |
Clean Flume |
771 |
132 |
Clean Inlet |
469.77 |
133 |
Clean / Grade Bar Ditch |
688.25 |
54 |
Contract Inspection |
99.75 |
8 |
Control Vegetation |
481.6 |
289 |
Dirt & Mud Removal |
269.25 |
42 |
Field Inspection ( No Condition ) |
880.8 |
1652 |
Fill Void |
0 |
5 |
Graffiti Clean Up |
78.97 |
25 |
Hydro Excavation |
113.5 |
14 |
Illegal Dumping Response |
23.5 |
9 |
Inlet Decal Install |
83.75 |
365 |
Inlet Inspection |
1293.035 |
10811 |
Inspect |
335.75 |
141 |
Inspect Channel / Flume |
640.85 |
1139 |
Larvicide Dunk |
3.6 |
11 |
Lid Replacement |
10 |
5 |
Locate Line |
21 |
20 |
New Installation |
32.5 |
3 |
On-Call |
8 |
1 |
Pipe Inspection - Engineer Project |
94.25 |
1 |
Pipe Inspection - Maintenance Issue |
68.75 |
32 |
Pipe Inspection - Postconstruction |
86 |
57 |
Pipe Inspection - Preconstruction |
100.25 |
72 |
Remove Beaver Dam |
18.5 |
3 |
Remove Debris or Obstacle |
817.75 |
90 |
Remove Tree Limbs |
531.5 |
60 |
Repair Drainage Pipe |
206.5 |