Miscellaneous Channel Improvements ( Park Row Location ) – Channel improvement to replace an existing failed concrete channel with a modular block channel which will also reduce residential flooding . Wimbledon Drive Drainage Improvements – drainage improvements to alleviate residential flooding Woodland Drive Erosion - Reach based streambank stabilization to reduce erosion and restore aquatic habitat as part of the Erosion Pilot Program . This project includes one home being purchased to mitigation the risk due to erosion . Project was closed out . Any future erosion improvements will be completed in VC ( A ) -1 Project .
The following projects were under construction during the reporting period :
� 2015 Bridge Repair ( Treasure Island , Copeland , & Center St ) – Erosion and bridge repair identified as part of TXDOT ’ s bridge inspection program . Treasure Island and Copeland bridge repairs were deemed unnecessary at this time . Center Street bridge improvements were included in the Johnson Creek Sewer Project .
� 2017 Miscellaneous Maintenance Phase 1 - Miscellaneous large maintenance projects at various locations .
Phase 1 includes storm drainage improvements at Running Brook Drive .
�
�
� �
�
Country Club Rd . Local Drainage and Channel Improvements ( South of Park Row ) – drainage improvements to alleviate residential flooding and repair creek erosion associated with the transition from concrete channel to natural creek . Includes Park Row location from 2017 Bridge Maintenance Project . Flood Mitigation Buyouts – Nine homes are being purchased and demolished utilizing FEMA grants or City funds to remove them from areas with a known flood hazard . Greencove Drainage Improvements – drainage improvements to alleviate residential flooding Sublett Creek Neighborhood Drainage Improvements ( Hollow Creek , Doty Lane , Redstone Dr ., and Suffolk Dr .) – drainage improvements to alleviate residential flooding . Upper Johnson Creek Dredging – The project involves the dredging of sediment from two City park ponds within the upper Johnson Creek watershed ( Gateway Park and Lakes of Matlock ), and the design of two grade control structures between the ponds to control future erosion and sediment transport .
The following projects were under design during the reporting period : �
�
�
�
�
�
2017 Bridge Maintenance - Annual contract to complete bridge maintenance identified by bridge inspections . Locations include Hardisty , Park Row , Ballpark , Beady and Dugan . This project is being completed in phases . 2017 Miscellaneous Drainage Improvements - Drainage improvements at various locations including : Shady Lane , Maywood Drive , and Ivycrest Trail to alleviate street and residential flooding . This project will be constructed in phases . 2017 Miscellaneous Erosion Projects - Erosion maintenance in earthen channels and ditches at various locations including the Arlington Municipal Airport , Green Acres Circle , Trail Lake Drive , Derby Hill Drive , Collins and Debbie , and Collins and MacGregor . This project will be constructed in phases . 2017 Miscellaneous Maintenance - Miscellaneous large maintenance projects at various locations including : Green Hill Drive channel and Running Brook Drive . This project will be constructed in phases . 2019 Erosion – Erosion Maintenance in earthen channels and at outfalls at various locations that are threatening public infrastructure . Locations include : Kee Branch at outfall from Willow Bend project ; outfall repairs in North Randol Mill Park ( north of I-30 ); outfall repairs at the intersection of Hinsdale and Whistler 2019 Ditches – Evaluation of maintenance of ditches in 10 different neighborhoods . This project will be designed and constructed in phases .