The Hammonton Gazette 10/02/19 Edition | Page 5

Boyer Avenue matters, including Frog rock, on council agenda Page 4 • Wednesday, October 2, 2019 • The Hammonton Gazette COUNCIL, from Page 1 “We started last week, last tues- day (september 17) i believe, at Boyer avenue on our land app. We began removing silt from trench four. We anticipate this going on probably this week and the early part of next week. We’ve had some great dry weather that’s working out well for us. We’re going to de- silt the trench, and we’re going to stack it up, and then kind of build up the sidewalls with the silt. if there’s time, we’re going to also do trench five this year. We’ve already rototilled trenches two and three. My goal is, over a three-year pe- riod, we’ll have all the silt removed from the trenches,” furgione said. furgione also made mention of the interceptor trench on the Boyer avenue property, and the work as- sociated with that. “We have the supplies ordered for our discharge pipe that is at the end of our interceptor trench. that project will go as soon as we’re done with our silt removal in our trenches,” furgione said. town engineer Mark Her- mann’s report featured four infor- mation items regarding the Boyer avenue area, which read as fol- lows: • Boyer avenue – 2019 addi- tional survey Work (arH p2019.0519): the survey and right-of-way mark-out of sewell avenue is complete; survey of Boyer avenue and the interceptor trench area for sanitary sewer ex- tension will be completed by the end of the week. as discussed at the pWtC meeting, the 7th street work will be held to a later date. • relocation of interceptor trench discharge (arH #p2019.0239): soil analysis results have been received and a prelimi- nary relocation plan has been de- veloped for review. this plan will be discussed at the pWtC meeting on september 19. • Boyer avenue – 2018 opti- mization phase i (arH #11- 50058): a draft version of this report was sent out on March 29, 2019. • frog rock Golf Course Legal action (arH #11-01000): adams, rehmann & Heggan developed a cost estimate and summary of the items that we believe frog rock has not completed in contravention to the 1999 Consent order and at- tended a federal hearing in regard to this matter on august 29. at this time, the judge has given both par- ties 30 days to review information submitted by frog rock counsel. We were not provided with a copy of this document, but can review if desired. another item of interest in fur- gione’s committee report regarded the status of the water tower proj- ects, which are moving along. “the water tower on Lincoln street has been drained. it was empty as of last Wednesday (sep- tember 18). Wells one and three are also off. Wells one and three and the water will not go back on serv- ice until the water tower painting is complete,” furgione said. furgione noted that water pres- sure is a concern during the project, but a flow meter has been installed on the fourth street tower to en- sure consistent pressure is main- tained throughout Hammonton. “every day we’re manually checking it. We’re making sure, if we need to turn on additional wells to support our pressure, we do it prior to us running into a problem. so far it’s been working,” furgione said. Council voted on a resolution to approve a lease between the town of Hammonton and Verizon Wire- less for up to three telecommunica- tions antennas to be raised on the fourth street water tower. this lease is for five years before an ad- ditional five year extension, in the amount of $39,600 per year, with a three percent guaranteed per annum increase. the same terms and conditions for the Lincoln street tower, with one exception: Verizon has agreed to reimburse the town any and all costs associated with the welding of the brackets to the bowl of the Lincoln street tower necessary to support their antennas. allied painting inc. will do the welding, and all associated costs will be paid by Verizon. “the initial design, that we all said ‘no’ to at public Works, they wanted to put the antenna on top of what i call the witch’s hat, on top of the point, which would have been disastrous, and build some sort of corral around it. then they wanted to turn their antennas up, which would block our logo. so, instead, we’re just going to turn the antennas down, and they’ll have support from underneath,” fur- gione said. Hammonton public Works Man- ager robert Vettese noted that talks with allied painting inc. pointed to a possible completion date. “in scheduling with the contrac- tor, we indicated that, as long as the weather holds out... hopefully that will be completed by early novem- ber, and then we’ll be able to fill the tank and turn on the water,” Vettese said. furgione commented on the color of the tower, which should not be any different after the paint- ing is finished. “the color will be very similar. it’s called philadelphia Gray. and they’ll do all the sandblasting and painting underneath the tarp. they’ll heat as needed. i think by thanksgiving we’ll be in good shape here,” furgione said. road projects were a major topic of discussion during the meeting. the first one mentioned was Wash- ington street, currently under con- struction. “right now, the majority of the utilities are in the ground... the ma- jority of the curb and sidewalk has been constructed. We’re waiting for the trenches to settle a little bit before we do final paving,” Her- mann said. the work on 14th street is also proceeding according to plan, which is to tie in the work being done by Hammonton with the work being done by folsom. “We did the first section in 2015, but we ran short. We were 550 feet short of folsom,” Hermann said. Hermann noted, however, that this work will not cost Hammonton residents any money. “all of the construction costs, in- spection costs... will all be covered under the grant, with no additional cost to the town,” Hermann said. Vettese introduced a new proj- ect, this one to take place on old forks road, from the White Horse pike to egg Harbor road, which will require a joint agreement with Winslow twp. this work will be done under a state program provid- ing local freight impact funds, which requires that traffic on qual- ifying roads musts be at least 10 percent heavy truck traffic. Vettese has been working with town plan- ner Kevin dixon on a traffic study of that area. “Between third street and egg Harbor road is really where is most of the truck traffic, and we didn’t want to get confused with the school traffic, because that gen- erates a lot of traffic between third street and the White Horse pike. so we’re trying to isolate it to that one section so we can maximize the amount of truck traffic,” Vettese said. the application for the fund is due by october 17, 2019. Vettese asked the council to authorize dixon to start the study, with a monetary amount of $4,005. “We had a joint meeting last week, and the superintendent of public works from Winslow town- ship representing the mayor, and they’re interested as long as the traffic counts match the grant re- quirements. We’ll have to move very quickly if we do meet the traf- fic counts. if not, we’ll have to wait until probably the summer to do those counts,” Vettese said. Vettese also noted that the rail- road bridge on old forks road is not going to be widened, but, given its precarious slope, some work may be done to ease the ap- proaches in either direction while maintaining track elevation. Vettese then gave an update on the 2019 roads project, and dis- cussed a preconstruction meeting held with arawak paving Co. “the first thing thus far was the concrete work, probably the sec- ond week or first week in october. they’ll probably start on Grape street and make their way over to Chestnut, and then to orchard street on the concrete work. paving work will follow soon thereafter. they might be able to do Gatto road, and start that first, then sindoni Lane; we’ll do that, also, then sections of first road, so we’ll have a couple of different contractors working at the same time. Hopefully everything will be completed there by late novem- ber,” Vettese said. during the discussion with council, Councilman Joseph Giralo indicated concern regarding the drainage work done on second road. “i’m not a roads guy, but i really think you’ve got to tack that up where there’s gutters so the water See rOADS, Page 9