The Hammonton Gazette 04/22/15 Edition | Page 5

$190K DOT grant for 14th St. repairs from Second Rd. to Folsom line Page 4 • Wednesday, April 22, 2015 • The Hammonton Gazette PWTC, from Page 1 news to the committee during the meeting, as there is $78.75 million available in the Transportation Trust Fund. “That was the second attempt by ARH, and we received money to do that project. I believe it is close to the estimate that was submitted. This is from Second Street to the Folsom line,” Barberio said. On April 20, Mayor Stephen DiDonato told The Gazette that the start of the project could take place sometime toward the end of the year. Barberio updated members of the committee on a home that was affected by a fire more than a year ago on 39 Centennial Drive. The homeowner didn’t have the property cleaned when asked to, and he was in court on Tuesday, April 14 where he was fined. “Our code enforcement officials issued a notice shortly after last month’s meeting. I think it was on March 17. The mayor [Stephen DiDonato] and I appeared in court on Tuesday. The homeowner pled guilty to a $21,000 fine and two weeks to clean up the property, plus reimbursement of the town for $1,500 for the fence that was installed. The judge ruled, if the individual cleans the property up in two weeks, the fine will be excused. The $1,500 comes back to us for the fence we installed. That was an outstanding issue that we took care of on Tuesday [April 14],” Barberio said. There have been requests from two residents for street lights, one on South Liberty Street and one on Pleasant Mills Road, according to Barberio. “I have given the electric company the pole numbers. They are going to get back to us with a cost to add street lights at those locations. The one on South Liberty Street, the neighbor had been complaining that the Woman’s Civic Club building has a lot of affairs, which they do, and they have a lot of street parking and it is dark. The other one was for Pleasant Mills Road, and the section there is really dark,” Barberio said. Barberio also provided an update on the work being performed at the Hammonton Municipal Airport, and stated it is nearly complete. “I met with the contractor this morning [Thursday, April 16]. The contractor is 95-97 percent done. He has the tarmac lights. He has all of the lights working properly. I was able to turn on the lights with my microphone. All the electrical components are completed. He was doing hydro seeding and grating around the ditches. It has gone really well. So, the lights have been upgraded to LEDs, all of the trenches have been completed, the tarmac now has lights so when you are moving airplanes around it is completely illuminated, especially when you are getting fuel. It is much safer and there is signage. So, this $870,000 grant, which the contractor bid just under $600,000, we were able to stretch it out and get all those items in there,” Barberio said. In the engineer’s report, Robert Vettese of ARH discussed two action items for the April 20 town council meeting. There was a status for wells one and three as work is ongoing. “The contractor has been working out on the site. We are still trying to shoot for that June 1 operation. I would say it is about 78 percent done. We are asking for $20,000, but only if we get reimbursed. If we find out something on that I will bring it up during the meeting [town council meeting]. The request is not to exceed $20,000, subject to NJDOT Spill Fund approval of the work,” Vettese said. The other potential action item was the Weymouth Road Drainage project. In December, council took action to extend the contractor, the service agreement to December of 2015, according to Vettese. “The county has basically acted on that now. What they have sent back is a contract amendment, so what we need and I talked with the legal department at the county, they said they really don’t need a resolution from the town, just a motion for the mayor to sign the three contract renewals,” Vettese said. Vettese and David Cella of ARH had an update on the piping, sanitary sewer, storm sewer and other utilities being performed on Grape Street, Pratt Street and the intersections. The April 15 deadline has passed, and the committee was deciding what action to take next. The contractor, Charles Marandino, is proposing an additional extension to the end of May, but there was already one extension granted in November for 75 additional days, which expired last week. “They [the contractor] gave us a revised schedule for the end of May. We have asked them to shorten that and get their paving done sooner. The question that hasn’t been raised yet is are we going to let them base [coat] one side and go back and top it off at a later date? But when they come in with a paving crew to start basing over they need to start fixing and topping on Grape Street,” Cella said at the April 16 meeting. Members of the committee met with the contractor on April 20 in order to get a clear vision of what needs to be completed with the ongoing lengthy road reconstruction project. Based on the contract, discussions on legal ramifications could come up at some point as well if deadlines are not met, committee members and professionals said during the two meetings. The new deadlines are May 30 for base course on Pratt Street and June 29 for top coat on Pratt Street, the committee said. Grape, Second and Packard Streets are expected to be completed by May 15, the committee said. “We have to have a meeting to find out where we are with this project. When are we going to wrap everything up and what are the issues that are holding us up at this point? We let them work through the winter and now April 15 has passed,” Councilman Edward Wuillermin said on April 16. The next Public Works and Transportation and Water and Se