The Civil Engineering Contractor November 2018 | Page 21

ON SITE Group’s Civils division, under CEO Archie Rutherford, is aimed at transforming it into a one-stop contractor. The Civils division specialises in the construction of roads and earthworks, as well as installation of services such as water, sewer, and stormwater reticulation. It has also established a Concrete division specialising in all forms of structural concrete work. “We have a substantial and growing pipeline of project work. I am confident that the group will grow to be in a position to compete with the large public construction companies in the near future. Apart from being majority black women-owned, most of our staff are young, which means they represent the next generation of management and technical expertise,” Moodley says. Scope of work There are currently between 50 and 60 people working on site at any time — a number which is anticipated to ramp up considerably in the medium term, before civils work ends in about one year. Motheo site agent Helgard Brink explains that Motheo has been tasked with Phase One of the development, encompassing the provision of bulk services of the 7.5ha site. This phase includes construction of about 3.8km of asphalt roads, requiring 36 000m 3 of earthworks and layer works. The scope of work also involves construction of 3 500m of stormwater piping, 1 900m of water pipes, and 500m of sewerage pipes, as well as four attenuation ponds requiring 8 000m 3 of excavation and waterproofing with HDPE (high-density polyethylene) liners. A multi-barrel portal culvert bridge construction over a perennial waterway adds to the complexity. A major component of the scope is the bulk electrical connections, requiring the upgrade of two municipal electrical substations to facilitate the development. There are two main intersections to be constructed, and some road widening, to facilitate access to the development. The much larger Phase Two will involve construction of the residential units and communal facilities. A total of 7.5ha of clearing had to be undertaken in preparation for the construction of the roads, attenuation ponds, and pipelines. The four attenuation ponds are to be constructed to manage water run-off caused by flash floods. Due to the large surface area of the site, about 4 000m 3 of attenuation volume will be created, as compared to a 500m 3 or 600m 3 volume on a more typical site. “We are catching the bulk of the water run-off on site, caused by the hard surfaces created on significant portions of the land. This will allow the overflow to be released back slowly into the natural water system. Every new development has to have such ponds to catch floodwater that, in the normal course of events, would naturally drain off, but which is prevented from doing so by consolidation of the surfaces,” says Brink. The bridge over the river requires 400m 2 of concrete and 45 tonnes of steel. Most of the concrete is precast for the bridge’s portal culverts, with three barrels of three-by-three culverts. In the past, the site had also been used as an informal dumping area. This has to be removed, and later taken off site to a solid-waste landfill site. The underlying dolomite required careful design consideration from what would be a typical plan. For instance, the water pipes had to be built with more expensive HDPE pipes and the sections welded together to ensure there was no leakage. “The site is highly sensitive due to its dolomitic nature, and dolomite doesn’t like water. We therefore needed special pipes that would not leak,” says Brink. The contractor was appointed on 20 April. Permits and way leaves were granted, and the contractor commenced construction on 28 May. Works are scheduled to be completed by 29 May 2019. The design of the works has also The project includes the construction of 3.8km of asphalt roads, requiring 36 000m 2 of earthworks and layer works. www.civilsonline.co.za CEC November 2018 | 19