The Civil Engineering Contractor April 2019 | Page 18

ON SITE was completed by October, when the installation of the electrical work began. The structural steelwork totals some 1 350 tonnes with concrete at 10 000m 3 and piping of 20km (14km in plant and 6km for the tailings dam). Nokeng Fluorspar Mine received two infrastructure grants from the Department of Trade and Industry (dti), amounting up to ±R18-million, for the improvements it brings to the public infrastructure. “Any work that one does, which has a public effect beyond your actual project, is eligible for a grant of up to 30%,” explained Wagner. Nokeng has also built a new intersection on the public road to grant access to its premises with turnoff lanes, resurfacing existing road, and constructing a new tarred road to its processing plant, with an improved water drainage system to drain water away from polluted zones. Construction challenges Roads through the plant Wagner, as “not everything is in the EPC package.” The mine and tailings storage facility were constructed by SepFluor, whilst the power line, roads, and plant were in the EPC as a single package. The life of mine is 19-years, which requires the construction of a main tailings dam that can cater for an approximate 20-year lifespan. The tailings dam wall will be lifted in different phases, with the height 16 | CEC April 2019 being increased in three stages as the level of tailings increases. The first lift is expected to be two years after commissioning. “The reason for this approach is to limit initial capital cost and also there’s a possibility that we may strip fine iron out of our tailings in future, which will reduce the volume of material in the tailings storage by 60–70%.” The steelwork phase commenced in May/June 2018 and most of it The target completion date was for February 2019, but construction has been delayed slightly for a number of reasons. Originally, the project was tendered to an Indian company back in 2014, which escalated the price to such an extent that close to the time of execution, SepFluor was no longer comfortable with the pricing. “We went back to the market and at that stage, all the construction houses in South Africa had insufficient work, resulting in them tendering low margins on the project.” Delays in the power line construction required Nokeng to bring in Jozi Power and to employ diesel generators to provide 3MW of power up until the Eskom power line was finally commissioned. Employment of local people is a challenge faced by every construction project. Wagner explained that initially only 300 workers were anticipated on site but, “We peaked www.civilsonline.co.za