The Civil Engineering Contractor April 2019 | Page 19

ON SITE Chemical plant In addition to the mine and processing facility near Rust de Winter, SepFluor also plans to construct a chemical plant in Bronkhorstspruit, which will beneficiate the product produced at the mine. Construction of the chemical plant is expected to start within the next two years. Nokeng Mine’s premium product will be acidspar, the key ingredient www.civilsonline.co.za in the manufacturing of hydrofluoric acid and a precursor to almost all fluorine compounds, including pharmaceuticals such as fluoxetine, diverse materials such as PTFE, and elemental fluorine itself. “Our plan has always been to develop the beneficiation of fluorspar by means of constructing a chemical plant that is currently in a bankable feasibility stage (BFS), to establish the financial and the technical requirements. We would then take the fluorspar produced at the Nokeng Mine and process it, in order to produce hydrofluoric acid, which is a very valuable commodity and a key ingredient of all fluorspar products that are manufactured worldwide,” explained Nokeng Mine’s project director, Johan Brits. The building of the Dr Lelau Mohuba Training Centre at Nokeng Mine has been as impressive as the other construction work on site. As part of the mine’s SLP, the 2 400m² building was built and equipped in just seven months at a cost of R17-million. More than 2 500 men and women from the nine local communities are expected to receive training in skills such as boilermaker/welder aide, fitter aide, electrician aide, and community house-building over the next 10 years at the Mining Qualifications Authority-accredited Dr Lelau Mohuba Training Centre. Tuition, study materials, transport, work clothing, and personal protective equipment totalling roughly R36 000 per trainee will be provided (free of charge) by the Nokeng Fluorspar Mine during the life of the mine. Some 56 trainees have already completed the various training courses and approximately half of these have been taken up in permanent employment on the mine. Those not employed on the mine will be equipped to find work elsewhere having both practical skills and a formal qualification that is sought after in the labour market. nn Magugu Mvula, Group 5 general manager – SA. last week (December 2018) at 1 100 with most of the civil crews demobilised.” There were nine communities involved in the project, all of them wanting to benefit from the Nokeng Mine. To manage this, Nokeng established an Engagement Forum to manage all communications and expectations. The Nokeng project has recognised communities within a 25km radius, although the Social and Labour Plan guidelines are vague on this subject, says Wagner, who notes that some communities (as far away as 100km) initially sought to be included. Nokeng has employed as many local community workers as possible and required every contractor to follow suit. There was little disruption to construction, with only a minor two-day stoppage due to HR practices at the joint venture contractor. Wagner says there are a number of ‘business forums’ that have been the cause of disruptions on many contractor sites around the country, but Nokeng’s policy is to deal only with authorised representatives through the Engagement Forum. “We put as much contact work back into these communities as possible and a major portion of the construction of the Dr Lelau Mohuba Training Centre was done by community businesses. Once the mine is operational, there will be long-term contracts for the community for services such as security and cleaning, as well as supplies of material into the mine.” Rob Wagner, CEO of SepFluor Limited, at Outwash Fan, with the mine’s process plant and related infrastructure in the distance. Professional team Client: SepFluor Main contractor: Group Five and DRA Architect: DRA Quantity surveyor: DRA Geotechnical and piling: DRA CEC April 2019 | 17