SSIP Annual Reports 2018 Annual Report | Page 10

10 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. PHASE 1 METRICS Total Budget Spent The scope, schedules, and budgets of SSIP’s baseline were revised in April 2018. SSIP management will undertake this exercise every two years coincidental with our budget cycle to refine scope needs and establish more accurate schedule and budget forecasts. We continue to make significant progress across all 70 projects in Phase 1 and below are metrics that demonstrate that progress across the Program. $2.261 Billion BUDGET $718M SPENT Project Count by Phase COMPLETED PLANNING (20 Projects) (8 Projects) $121M $166M CLOSE-OUT $175M (9 Projects) DESIGN $1,737M CONSTRUCTION $636M (12 Projects) TOTAL (14 Projects) $2.979B (70 Projects) BID & AWARD $144M (7 Projects) SSIP Phase 1 Completion 28.4 % All data is through December 2018 0 100