Safe Streets Arlington Plan Safe Streets Arlington Plan | Page 206

External Stakeholder Committee Meeting # 3 2-3:30 p . m ., Wednesday , September 18 , 2024 Virtual Meeting
MEETING SUMMARY
City Representatives Ann Foss , Planning and Programming Manager Jana Wentzel , Principal Planner
Project Consultants Josh Peterman , Fehr & Peers Natalie Daugherty , Fehr & Peers Nicole Waldheim , Fehr & Peers Mason Shoaf , Kimley-Horn Leigh Hornsby , Public Information Associates
MEETING PRESENTATION Ann kicked oU the meeting at 2 p . m . and reviewed the agenda , which included :
• Recap progress on the plan
• Review stakeholder and public input
• Share plan priorities
• Discuss implementing the safety action plan
• Wrap-up and next steps
Next , she provided a review of progress to date .
The Safe Streets Arlington timeline illustrates this project is currently in the Community Engagement and Plan Development & Adoption phases . Community Engagement ends in October 2024 . Adoption is scheduled in November 2024 .
D-52