PROJECT
Supplied by RPM Consulting Engineers project

ENGINEERING AN OPERATIONAL CHILLER PLANT UPGRADE WITHOUT BUSINESS INTERRUPTION

By Barry J. Wallett Pr. Eng., RPM Consulting Engineers
The Interchange, 22 Skeen Boulevard, Bedfordview: A case study in phased chilled water plant modernisation.

Replacing the central cooling plant of an occupied commercial office building presents one of the greatest challenges facing consulting engineers and HVAC contractors. Unlike new developments, refurbishment projects require construction activities to take place while tenants continue normal operations, often with minimal tolerance for service interruptions.

The Interchange, located at 22 Skeen Boulevard in Bedfordview, Johannesburg, presented precisely this challenge. The existing chilled water plant had reached the end of its useful service life and required complete replacement. However, uninterrupted air conditioning was critical to maintaining tenant comfort and protecting business continuity throughout the construction period.
To address these constraints, RPM Consulting Engineers developed a two-phase implementation strategy that enabled the existing cooling infrastructure to remain operational while progressively replacing the plant. The project incorporated highefficiency air-cooled screw chillers, a new primary-secondary pumping arrangement, thermal buffer storage, upgraded controls and comprehensive commissioning procedures.
One of the most technically demanding aspects of the project was connecting the new chilled water plant into the existing live pipework without draining the entire building distribution system. This was achieved using nitrogen pipe freezing techniques, allowing isolation of the mains while avoiding significant downtime and eliminating the need to refill and recommission the entire hydraulic network.
The completed installation represents a modern, energyefficient chilled water system capable of meeting the building ' s long-term cooling requirements while providing improved reliability, maintainability and operational flexibility.
PROJECT BACKGROUND The Interchange is a premium commercial office development, fully air conditioned using a central chilled water system serving multiple air handling units throughout the development.
Like many commercial buildings commissioned more than a decade ago, the original plant had begun to exhibit increasing maintenance requirements, declining energy performance and growing concerns regarding long-term reliability.
Rather than continuing with reactive maintenance, Redefine Properties elected to undertake a complete replacement of the central chilled water plant.
The objectives of the upgrade included:
• Improve overall energy efficiency.
• Increase plant reliability.
• Reduce future maintenance costs.
• Introduce modern microprocessor controls.
• Improve part-load performance.
• Allow future operational flexibility.
• Complete the works while maintaining cooling to occupied areas.
EXISTING CHALLENGES Refurbishment projects differ significantly from new installations because the existing services cannot simply be switched off for extended periods. Several engineering challenges had to be addressed before detailed design commenced.
Continuous building operation: The building remained fully occupied throughout construction. Any prolonged interruption of chilled water services would have affected tenant comfort and potentially interrupted business operations. Maintaining cooling therefore became one of the primary design constraints.
Existing hydraulic network: The existing chilled water pipework extended throughout the building. Draining the complete system would have required: