RACA Journal April 2020 | Page 54

Projects side of the room was fitted with perforated stainless steel plates to allow for the equal distribution of air from one side of the room to the other. This is critically important to ensure that the product dries evenly and consistently across the entire room and thus ensure a superior product. SAVINGS FROM THE SYSTEM Minnaar Rigging the AHU into position with limited space. On 17 November the first load of biltong was placed in the room to trial its performance. This was owed to the fact that, during all commissioning phases, there was some fine tuning and fault finding to be done on the system once it was operating under load. By 28 November most of the commissioning niggles were resolved and the first batch of high-quality product was dried in the room. DEALING WITH CHALLENGES One of the most challenging aspects of this project was the timeline and the fact that this precluded the utilisation of any desiccant dehumidification equipment due to equipment lead times. The dehumidification and room conditioning were achieved purely by mechanical dehumidification and reheat. In order to achieve the correct amount of airflow over the product a false ceiling plenum was constructed and either Due to the significant time constraints on the project there was not sufficient time to optimise and look at all possible energy optimisation strategies. AMC did however perform a review of future potential optimisation and have allowed for these in the design at minimal initial cost. Some of these strategies include the use of waste heat from the ammonia plant for primary reheat of the dry off coil air as well as the utilisation of external ambient air under specific conditions to reduce the dehumidification load on the AHU. In some instances that ambient air absolute humidity content is low enough to be utilised directly under 100% fresh air conditions. Although no ducting or coils were installed for the above potential modifications, space was left for these in future in the form of a fresh air damper and physical space in and around the AHU. ONE OF A KIND SYSTEM What made this project special is that it was completed under stringent time constraints; the contractors and equipment suppliers worked extremely well as a team; and the client in the end had a well-designed and installed system that operates as required and optimally. It was a great sense of achievement to hear from the client that their customer was happy with the quality of the final product and that internally they were pleased by the performance of the room as a whole. There was a significant improvement in the final product due to the correct drying regime and room conditions. RACA ABOUT THE AUTHORS • • The loading bay for loading once the biltong is dried, stored and packed ready for delivery, nationwide. 52 RACA Journal I April 2020 Andrew Minnaar, director at AMC Engineers, is a qualified professionally registered, mechanical engineer, and a member of ASHRAE and the South African Refrigerated Distribution Association (SARDA). Michael Barbosa is a director of abattoirs, food processing and private clients at SCIP Engineering Group. Qualified as a civil engineer and registered as a Professional Engineer with the Engineering Council of South Africa (ECSA). He is also a director at Matbar, who developed the project. www.hvacronline.co.za