Floridan well drilling underway for Range Line Water Treatment Facility
Drilling has commenced on the first Floridan well as part of the larger Range Line Water Treatment Facility project. This well is the first of six planned for the new plant, which will enhance water supply capabilities for the region. Additionally, three more wells will be drilled to provide raw water for the James E. Anderson Water Treatment Facility.
NP-13 startup testing scheduled
Startup testing for NP-13 is expected to begin in late February or early March. Following successful testing, the old lift station will be demolished, marking another milestone in system modernization.
Southport Force Main project completed
The Southport Force Main project has been completed and the team is working with the Florida Department of Environmental Protection( FDEP) to secure reimbursement under the grant program.
Prineville Water Treatment Facility injection well nears completion
The injection well at the Prineville Water Treatment Facility is making significant progress, with drilling reaching a depth of 2,850 feet. The final depth is expected to be 3,350 feet. We anticipate breaking down the rig in April, after which above-ground construction will begin. www. CityofPSL. com / Utility