Protection Engineering Basics and Schemes Protection Engineering | Page 155

 You can also view the injected current values on Relay front panel It is not necessary that your test kit is operate via software, like sverker 750/760 in which you just need to make connection and execute test directly, but remember software make work easy , safe and more efficient. 5.4.2 Drop Off Test:  When test perform successfully , you can DE energize relay with help of Test kit, we will put test kit injection current value back to Zero manually or via software, you can observe relay Yellow Light indication of Trip/pick up will vanish  Check zero voltage status, after which you can handed it back to concern authorized engineer or worker 5.4.3 Pickup/Drop off Test: It is the combination of Pick up and Drop off Test, executed at the same time, and values are noted. Same Pick up Test connections will be used. pg. 155