Palm Beach Undergrounding Master Plan COMPLETE MP Online-v5 | Page 201

Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 5 South Item No. Description Amount $1,560,000 1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $510,000 3 Comcast Overhead to Underground Conversion $330,000 4 Roadway and Private Property Restoration $1,120,000 5 FPL Direct Costs $1,890,000 6 AT&T Direct Costs $250,000 7 Comcast Direct Costs $110,000 8 FPL Service Conduit (Private Property) $270,000 9 Engineering/Permitting/Surveying $510,000 10 Construction Administration $300,000 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $150,000 12 ($840,000) Subtotal Estimate – Today’s Dollars $6,200,000 Subtotal Estimate – Considering Inflation $6,900,000 Contingency $640,000 Total = $7,540,000 TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 175