Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 5 North Item No. Description Amount $1,250,000 1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $430,000 3 Comcast Overhead to Underground Conversion $300,000 4 Roadway and Private Property Restoration $1,130,000 5 FPL Direct Costs $1,320,000 6 AT&T Direct Costs $310,000 7 Comcast Direct Costs $140,000 8 FPL Service Conduit (Private Property) $340,000 9 Engineering/Permitting/Surveying $440,000 10 Construction Administration $290,000 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $130,000 12 174 | CHAPTER TWELVE ($700,000) Subtotal Estimate – Today’s Dollars $5,400,000 Subtotal Estimate – Considering Inflation $6,000,000 Contingency $550,000 Total = $6,550,000 TOWN OF PALM BEACH