Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 1 South Item No. 1 1A 2 2A 3 3A 4 4A 5 Description Amount $1,860,000 FPL Overhead to Underground to Conversion FPL Overhead to Underground to Conversion (Ibis Isle) $300,000 AT&T Overhead to Underground to Conversion $280,000 AT&T Overhead to Underground to Conversion (Ibis Isle) $120,000 Comcast Overhead to Underground to Conversion $70,000 Comcast Overhead to Underground to Conversion (Ibis Isle) $80,000 Roadway and Private Property Restoration $460,000 Roadway and Private Property Restoration (Ibis Isle) $150,000 $3,010,000 FPL Direct Costs FPL Direct Costs (Ibis Isle) $370,000 6 AT&T Direct Costs $220,000 7 Comcast Direct Costs 8 FPL Service Conduit (Private Property) $100,000 9 Existing Utility Adjustment $630,000 10 Engineering/Permitting/Surveying $740,000 11 Construction Administration $240,000 12 11 13 Legal Fees Credits FPL Credit – 25% GAF Waiver $180,000 5A $50,000 ($1,370,000) Subtotal Estimate – Today’s Dollars $7,500,000 Subtotal Estimate – Considering Inflation $7,500,000 Contingency $640,000 Subtotal = $8,140,000 Total (Lake Worth Segment) = $420,000 Grand Total (Excludes Lake Worth Segment) = $7,720,000 TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COSTS | 167