Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 1 North Item No. Description Amount 1 FPL Overhead to Underground Conversion $940,000 2 AT&T Overhead to Underground Conversion $320,000 3 Comcast Overhead to Underground Conversion $220,000 4 Roadway and Private Property Restoration $860,000 5 FPL Direct Costs 6 AT&T Direct Costs $240,000 7 Comcast Direct Costs $100,000 8 FPL Service Conduit (Private Property) $260,000 9 Engineering/Permitting/Surveying $590,000 10 Construction Administration $240,000 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $100,000 12 166 | CHAPTER TWELVE $1,160,000 ($540,000) Subtotal Estimate – Today’s Dollars $4,500,000 Subtotal Estimate – Considering Inflation $4,500,000 Contingency $400,000 Total = $4,900,000 TOWN OF PALM BEACH