Table 4 Anticipated Construction Sequence

Table 4 Anticipated Construction Sequence

Year Project Area Land Use Major Work Elements
2017 Phase 1 North Single Family Residential Undergrounding, Street Lighting, Watermain, Drainage 2017 Phase 1 South Multi-Family Residential Undergrounding, Drainage, Street Lighting 2017 Elsewhere in the Town
Australian Avenue sanitary sewer, Lake Trail Improvements, Ocean Outfall abandonment, Pump Station Improvements, FPU Gas Main Replacement, Southern Boulevard Bridge Replacement
2018 Phase 2 North Single Family Residential Undergrounding, Street Lighting, Watermain 2018 Phase 2 South Single Family Residential Undergrounding, Street Lighting, Watermain, FPU Gas Main Replacement, Southern Boulevard Bridge Replacement
2018 Elsewhere in the Town 2019 Phase 3 North Single Family Residential Undergrounding, Street Lighting, Watermain
Demolition and removal of overhead utilities from Phase 1, Mast Arm Replacement / Upgrade, Pump Station Improvements, FPU Gas Main Replacement, Bradley Place Improvements
2019 Phase 3 South Single Family Residential Undergrounding, Street Lighting, Watermain, Pumps Station Improvements 2019 Elsewhere in the Town
Demolition and removal of overhead utilities from Phase 2, Pump Station Improvements, FPU Gas Main Replacement, Southern Boulevard Bridge Replacement, Mast Arm Replacement / Upgrade
2020 Phase 4 North Single Family Residential Undergrounding, Street Lighting, Watermain
2020 Phase 4 South
2020 Elsewhere in the Town
Mixed-Use Commercial / Residential
Undergrounding, Street Lighting, Watermain, Pump Station Improvements
Demolition and removal of overhead utilities from Phase 3, Pump Station Improvements, FPU Gas Main Replacement, Southern Boulevard Bridge Replacement
2021 Phase 5 North Single Family Residential Undergrounding, Street Lighting, Watermain
2021 Phase 5 South
2021 Elsewhere in the Town
Mixed-Use Commercial / Residential
Undergrounding, Street Lighting, Watermain, Signal Interconnect, FPU Gas Main Replacement
Demolition and removal of overhead utilities from Phase 4, Pump Station Improvements, Southern Boulevard Street Lighting, FPU Gas Main Replacement, Southern Boulevard Bridge Replacement
2022 Phase 6 North Single Family Residential Undergrounding, Street Lighting, Watermain
2022 Phase 6 South
Mixed-Use Commercial / Residential
Undergrounding, Street Lighting, Watermain, Signal Interconnect
2022 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 5 2023 Phase 7 North Single Family Residential Undergrounding, Street Lighting, Watermain
2023 Phase 7 South
Single Family / Multi-Family
Undergrounding, Street Lighting, Watermain
2023 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 6
2024 Phase 8
Mixed-Use Commercial / Residential
Undergrounding, Watermain, Demolition and removal of overhead utilities 2024 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 7
TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT