Our Plans for 2021/22 | Page 48

1.3 ROADS & DRAINAGE Our projects 2021 / 22
Project ID
Urban / Rural
Asset work type
Project name
Project type
Local area
Indicative scope
Start End Length
Cost estimates
($)
1.3
Rural
Renewal
Hoganthulla Road - gravel resheet
Gravel resheet
Mitchell
ch . 56
ch . 76
20kms
1.3a
Rural
Renewal
Redford Road - gravel resheet /
Gravel resheet
Mitchell
ch . 20.54
ch . 38.44
17.9kms
widen pavement
1.3b
Rural
Renewal
Sandlewood Downs Road
Gravel resheet
Surat
ch . 2.48
ch . 3.60
1.12kms
gravel resheet
1.3c
Rural
Renewal
Riversleigh Road gravel resheet
Gravel resheet
Surat
TBC
TBC
0.7kms
1.3d
Rural
Renewal
Munnaweena Road gravel
Gravel resheet
Mitchell
Varies
Varies
3kms
resheet ( various sections )
u1.3j
Rural
Renewal
Teelba Road - Gravel resheet
Gravel resheet
Surat
Sections
To ch . 20
1.3e
Rural
Renewal /
Upgrade
1.3f
Rural
Renewal /
Upgrade
48 Our plans for 2021 / 22
Mt Everdale Road ( 246 ) - Gravel Resheet and Drainage Upgrade - APLNG
Kangaroo Creek Road - Santos GLNG
1.3g
Rural
Renewal
Angry Jungle Road - Santos
GLNG
1.3h
Rural
Renewal /
Upgrade
McLennans Road - Santos GLNG
Gravel resheet
Gravel resheet
Gravel resheet
Gravel resheet
Yuleba
Yuleba
Yuleba
Yuleba
2,774,121
1.3i
Rural
Renewal
Restoration of Essential
Flood restoration
Public Asset - Flood Damage ( completed by 30 June 2022 )
Regional
16,064,731
Bitumen Extensions - excluded from recommended budget due to requirement to present " minimum / critical " projects only
1.3j
Urban
Renewal
Annual Urban Street Reseal
Bitumen reseal
1.3k
Rural
Renewal
Program
Annual Rural Road Reseal
Bitumen reseal
Regional
2,484,360
Program
Regional
1.3l
Rural
Renewal
Ashmount Road - Bitumen Rehabilitation
1.3m
Rural
Renewal
Bulk special maintenance -
bitumen rehab
1.3n
Rural
Renewal
Beverley Road - Bitumen
Rehabilitation
1.3o
Rural
Renewal
Bindango Road - Bitumen
Rehabilitation
1.3p
Rural
Renewal
Bollon Road - Bitumen
Rehabilitation
1.3q
Rural
Renewal
Gunnawarra Road - Bitumen
Rehabilitation
1.3r
Rural
Renewal
Six Mile Road - Bitumen
Rehabilitation
1.3s
Rural
Renewal
Tiger Scrub Road - Bitumen
Rehabilitation
1.3t
Rural
Renewal
Warrong Road - Bitumen
Rehabilitation
1.3u
Rural
Renewal
Westgrove Road - Bitumen
Rehabilitation
1.3v
Rural
Renewal
Womblebank Gap Road -
Bitumen Rehabilitation
1.3w
Urban
Upgrade
( 1 ) Roma CBD Asphalt Upgrade
Program - Hawthorne Street
1.3x
Urban
Renewal
Fifth Avenue Injune - Hutton to
Ronald - Both Sides
1.3y
Urban
Renewal
Second Avenue Injune - Ronald
to Hutton - Both Sides
1.3z
Urban
Renewal
Louisa Street Mitchell - Dublin
to Short - Western Side
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Bitumen rehabilitation
Kerb and channel
Kerb and channel
Kerb and channel
Roma ch . 0 ch . 9.500 9.5kms
Regional
Roma 2.8kms
Roma
ch . 6.971
ch . 8.753
1.782kms
Mitchell
ch .
ch . 52.000
3.615kms
48.385
Mitchell
ch . 3.500
ch . 5.920
2.42kms
Roma
ch .
ch . 7.900
1.96kms
5.940
Roma
ch . 0
ch . 2.800
2.8kms
Mitchell
ch .
ch . 24.286
0.742kms
23.544
Injune
ch . 8.800
ch . 12.660
3.86kms
Injune
ch .
ch . 36.329
35.550
Roma
McDowall
Bowen
Injune Hutton Ronald
Injune Ronald Hutton
Injune Dublin Short
Bitumen Extensions to Kerb - excluded due to requirement to present " minimum / critical " projects only
0.779kms
TBA
5,944,820
275,000