Selma Herndon Elementary School |
ID |
Improvement |
Construction Cost |
Project Cost |
ID |
Improvement |
Construction Cost |
Project Cost |
Building Site and Community Improvements 23,466,000 29,027,000
Building Improvements 20,394,000 25,227,000
A-CANOPY Entrance Canopy . 1,200 SF 69,900
A-REMOD
" Bldg A Remodel . 2,450 SF . Reconfigure all Rooms . Larger Accessible Staff Restrooms . Increase Nurse Office Suite . Move Psychologist next to Nurse "
1,071,000
|
H-ROOF See Detail A for scope of work . 1,077,200
J-WALKS See Detail A for scope of work . 13,800
J-CANOPY See Detail A for scope of work . 60,600
J-REMOD See Detail A for scope of work . 369,300
J-ROOF See Detail A for scope of work . 1,077,200
|
||||||
A1 " Bldg A1 Admin Addition . Front office , teacher work room . 1,350 SF " 786,900 |
K-WALKS See Detail A for scope of work . 13,800 |
||||||
A2 Bldg A2 Library Addition . Reading Room . 1,240 SF . 722,800 |
K-CANOPY See Detail A for scope of work . 60,600 |
||||||
Ab-REMOD
MAKER SPACE 1,000 SF . Cabinets with counters all walls . New wall , ceiling and floor finishes . LED Lights . Power and Data at 4-feet on center .
291,400
B-WALKS See Detail A for scope of work . ( 2017 ) 24,500
B-CANOPY See Detail A for scope of work . 107,100
B-REMOD See Detail A for scope of work . 416,200
B-ROOF See Detail A for scope of work . 1,213,800
B1 Modular Restrooms . 480 SF ( 2017 ) -
C-WALKS See Detail A for scope of work . ( 2017 ) 13,800
C-CANOPY See Detail A for scope of work . 60,600
|
K-REMOD See Detail A for scope of work . 369,300
K-ROOF See Detail A for scope of work . 1,077,200
M1-Portables
" Replace Nine ( 9 ) Portable Buildings with Ten ( 10 ) Classrooms 28 ' x37 ' with Sinks & Casework . Toilets , Storage Room & Custodian Space . Building Area 11,500 SF , Site Concrete 5,000 SF , Chain Link Fence + Mow Strip 50 LF ."
2,185,800
Pc-MCOE Relocate MCOE Portable Building . Electrical , Water , Sewer . 21,900
TEACHING WALL
" Teaching Wall Cabinets / Storage . 20 Locations , each 22 Feet Long x 9 Feet Tall . Teaching surface to include a 16-Feet Wide Sliding Marker Boards , with bookcases behind the marker board , and set on 30 "" deep base cabinets . Storage Cabinets above the slidin "
291,400
DOORS Remove and replace exterior hollow metal doors and hardware , 20 locations 43,700
|
||||||
C-REMOD See Detail A for scope of work . 369,300
C-ROOF See Detail A for scope of work . 1,077,200
Cr-ELECT Replace Electrical Panels / Breakers ( 2017 ) 655,700
E-REMOD
Remodel Space into a Music Room . Finishes , Cabinets , Doors & Hardware , HVAC , LED Lights , 1,700 SF
495,400
E-ROOF Replace Roofing System , 1,700 SF 61,900
F-POWER
F-KITCH
Remove & Replace Old " Zinsco " brand Power Panels in Buildings , and their associated feeders back to Electrical Yard MSB
Kitchen Remodel , 2,150 SF . Upgrade Equipment and Walk-In Cooler / Freezer . Accessible Toilet Room and Locker Room .
655,700
626,600
F-SOUND Replace Sound System ( 2017 ) 196,700
F-ROOF Replace Roofing System , 6,500 SF 236,800
G-WALKS See Detail A for scope of work . 13,800
G-CANOPY See Detail A for scope of work . 60,600
G-REMOD See Detail A for scope of work . 369,300
G-ROOF See Detail A for scope of work . 1,077,200
H-WALKS See Detail A for scope of work . 13,800
H-CANOPY See Detail A for scope of work . 60,600
|
SIGNS
" Add Accessible Room ID Signs , Add Accessible Toilet Room Signs . Campus Wide ."
26,500
FANS Remove and Replace all exhaust fans in toilet rooms . 10 locations . 14,600
HVAC
TECH-SC
TECH-HC
TECH-IDF
VIDEO
POWER
" Remove and Replace HVAC Equipment & Equipment Curbs . Campus Wide . Circa 1997 "
" Technology , Structured Cabling . Replace the Structured Cabling system between the school site Main Distribution Frame and the utility service provider . Quantity : Fiber Optic Cables 12-MMC / 12-SMC , and a 25 Pair twisted cable copper backbone "
" Technology , Horizontal Cabling Replace the Horizontal Cabling system between the Intermediate Distribution Frame and the data drops . Cat-6e cable at 1-1 / 4 "" pathway , or Cat-6 if pathway is 3 / 4 " ". Quantity : 40 % of the campus , or 5 Drops per Classroom ."
" Technology , IDF Room Cooling . Install a cooling system at the technology IDF cabinet locations . Provide dedicated electrical power circuits and a battery back-up UPS system . Quantity : 4 locations at each school site . "
" Provide a Video Surveillance system at the campus . Two ( 2 ) Cameras for each permanent buildings . No cameras at portables ."
Remove & Replace Old " Zinsco " brand Power Panels in Buildings , and their associated feeders back to Electrical Yard MSB
568,300
36,400
131,100
21,900
35,000
947,200
CLOCKS Replace Clock System . Wireless Analog Synchronous Clocks 47,400
P . A .
" Add new Public Address system . Speakers in all Classrooms and occupied spaces . 8 Exterior Horns "
284,200
|
||||||
H-REMOD See Detail A for scope of work . 369,300 |
F . A . " Replace Existing Fire Alarm System , District Standard - Gamewell FCI " 378,900 |
Hr-REMOD |
" Move psychologist to Admin Office Remodel . Use space as P . E . Storage Room . 420 SF " |
122,400 |