Section Three
F a c i l i t y
Livingston Union School District | Facilities Master Plan
A s s e s s m e n t s
Campus Park Elementary School
ID
Construction
Cost
Improvement
Site Improvements
2,959,000
1-PRKG
Parking Lot 1 Reconfiguration
151,500
2-PRKG
Parking Lot 2 Reconfiguration
419,700
3-PRKG
Parking Lot 3
373,000
4-PRKG
8th Street, Off Site Drop Off Lane
86,300
5-PRKG
H Street, Off Site Drop Off Lane
58,300
1-COURT
Play Court 1 relocated to a new location
23,300
1-SHADE
Play Area 1 Fabric Shade Structure
19,700
2-PLAY
Play Area 2 relocated to new location with Fabric Shade Structure
149,000
AMP
Amphitheater
163,500
A-CONC
Building A concrete walks. Remove and replace
58,300
A-GATE
Main Entrance Gate and Entry
10,300
A-TURF
Remove concrete walks and increase turf area.
28,400
A-SHADE
Two (2) Metal Covered Shade Structures.
B-YARD
Kindergarten Play Yard remodel
C-CONC
Building C concrete walks. Remove and replace
58,300
D-CONC
Building D concrete walks. Remove and replace
78,100
E-CONC
Building E concrete walks. Remove and replace
46,600
FNCE-E6
Replace Eastern Chain Link Fence, 6-Feet Tall x 2" Fence Fabric and Concrete
Mow Strip.
23,300
FNCE-E8
Replace Eastern Chain Link Fence, 8-Feet Tall x 1" Fence Fabric and Concrete
Mow Strip.
14,600
FNCE-N8
Replace Northern Chain Link Fence, 8-Feet Tall x 1" Fence Fabric and Concrete Mow Strip.
94,000
FNCE-W6
Replace Western Chain Link Fence, 6-Feet Tall x 2" Fence Fabric and Concrete
Mow Strip.
89,600
FNCE-W8
Replace Western Chain Link Fence, 8-Feet Tall x 1" Fence Fabric and Concrete
Mow Strip.
14,600
H-STREET
H Street Extension
553,700
P-COURT
"1) New Basketball Backstops, 8 locations
2) Pavement, 16,000 SF, with 360 LF Concrete Curb & 180 LF Concrete
V-Gutter"
163,200
P-DRINK
Filtered Water Fountains at 7 locations. Accessible Hi-Low Drinking Fountains,
Cane Rails
Project
Cost
3,661,000
ID
Construction
Cost
Improvement
Community Improvements
SB-FIELD
Soft Ball Field with back-stop, dug-outs and a set of 5-row bleachers
T-300M
"300-Meter Track. 7-meters Wide with 18,000 SF of Track Clay Surface.
Regrade in-field turf, adjust sprinklers & re-seed, 62,000 SF. Field drainage
system at perimeter and 7,000 SF of 4"" Thick Concrete "
Totals
Project
Cost
204,000
252,000
14,890,000
18,419,000
29,100
174,900
100
246,300
35,700
25