Kingsgate Park Sports Centre Schedule & Costs | Page 3
K I NG S G AT E PA R K
Next stages
The Kingsgate Park Project will be delivered over several phases.
PHASE 1: Support Departments PHASE 2: New Sports Centre
2016 2019
July
Public consultation began Late summer
Demolition of existing Physical
Education Centre
2017
PHASE 3: Design Technology
and Sanatorium
Once the new Sports Centre has been delivered,
attention will shift in due course to
Construction of new Sports Centre commences
Feb
Planning application submitted
Comprising:
•
•
•
•
Design Technology extension
Design Technology refurbishment
Construction of a new Sanatorium
Redevelopment of Antrim House.
• Swimming Pool building
• Sports Hall building
• Fitness Suite.
August
Planning consent awarded
2018
Late summer
Building works commence
2022
After relocating vehicular access from
Kingsgate Road to Norman Road,
End
Sports Centre complete
Total cost of Sports Centre:
£40,973,000
onstruction of Support Departments’
C
buildings:
•
•
•
•
•
•
•
2023
Works Department
Central Purchasing Department
Energy Centre
Laundry
Grounds
Furniture Store
Waste and Recycling.
Total cost of preliminary work
and construction of Support
Department buildings:
Conversion of existing Fives Courts
to classrooms
Total cost of new classrooms:
£3,177,000
£4,942,000
The timings and costs detailed above are based on estimates at October 2017 and may be subject to change.