1992 - 1995 DOE / PSA - Shift Control Engineer Whitehall
AP for the operation and maintenance of a 9Mw standby power station and associated HV and LV switchgear in all government buildings in Whitehall as well as the operation and maintenance of both Rotary and Static UPS systems . I was AP for the Whitehall HTHW district heating system . I was the lead engineer working with the consultants in the planning of the refurbishment of MOD main building . This work included looking at both the heating and electrical load within the building to enable correct sizing of gas turbines and waste heat and secondary boilers for the proposed combined heat and power plant to be installed .
Professional Skills & Experience
Authorised Person - Electrical
Authorised Person - Aeronautical Ground Lighting ( AGL )
1985 - 1992 DOE / PSA – Technical Officer ( M & E )
Technical officer for various sites in the South of England . AP duties electrical , HV ring renewal at an RAF Station , AP mechanical for the replacement of boilers , AP electrical for airfield lighting .
1984 - 1985 DOE / PSA – Mechanical Fitter
Carried out maintenance and overhauls to diesel generating plant and water pumping stations in various camps in the Falkland Islands .
1975 - 1984
Authorised Person - Mechanical Systems
Authorised Person - Petroleum ( Class 2 and Class 3 Fuels )
Authorised Person - Confined Spaces
Authorised Person - Dental Air Vaccuum Systems
DOE / PSA Apprentice Mechanical Fitter
Aldershot Military Power Station carrying out maintenance on large marine diesel generating plant and associated waste heat boilers , steam boilers and pumps , and maintenance of oil filled HV switchgear .