Q98.
Section
c
5-1 Project management
Answer
The number of days required to perform the applicable work is calculated using the “Table:
List of work necessary for version upgrade.”
Work No.
Description
Work days
S1
System backup
2
D1
Data extraction
2
D2
Data conversion
2
H1
Hardware procurement
2
H2
Build hardware environment
2
S2
Install application software
1
S3
Customize application software
2
D3
Load data
1
S4
Operational test
3
Total
17
Q99.
Section
c
···=3−1
···=2−1
5-1 Project management
Answer
Use the arrow diagrams to clarify the work and number of days required for work for Ms. C
and Ms. D.
Ms. D
Ms. D
D1: 2 days
D2: 2 days
S1: 2 days H1: 3 days H2: 2 days S2: 2 days S3: 2 days
Ms. C
Ms. C
Ms. C
Ms. C
Ms. C
D2: 1 day
S4: 3 days
Ms. C
Ms. C
Ms. D
Ms. D
The number of days required for work performed only by Ms. C is: 2 days (S1) + 3 days (H1)
+ 2 days (H2) + 2 days (S2) + 2 days (S3) = 11 days.
The number of days required for work performed only by Ms. D is: 2 days (D1) + 2 days (D2)
= 4 days. However, since Ms. D performs the work concurrently with Ms. C, the number of
days is not used in the calculation.
In addition, the number of days required for work performed together by Ms. C and Ms. D is:
0.5 days (D3) + 1.5 days (S4) = 2 days.
Therefore, the number of days required for the work is 11+2=13 days.