Figure 16 : A mobilisation plan .
d . Prepares crew service contracts and submits them for approval with copies for the crew . e . Passes new sets of coveralls to all crew members , and f . Passes any necessary items for the project to crew members .
3 . Logistics and store team : a . Prepares and packs all required load out items for the project and pass them to the crews or arranges immediate shipment . b . Prepares packing lists and delivery notes for the ROV system to be picked up by the agent , c . Responds to all enquiries by the project engineer . d . Helps the project engineers inspect the workshop containers ensuring they contain all the system spares .
4 . Base technicians ’ team and engineers : a . Help the project engineers prepare all load out items . b . Help the project engineers with system maintenance prior to the system audit . c . Ensure all systems are functioning to specification and are tidy and clean .
Figure 17 : ROV maintenance .
d . Help the project engineers and the tools contractor to perform a bench test .
SECOND PHASE The ROV system technicians and base technicians , and project engineers normally reach the port three days before sailing to the project site . By this time , the ROV should already be onboard the vessel / oil rig with all necessary sea fastenings completed by the vessel contractor .