IM 2020 September 20 | Página 81

HIGH PROFILE was a deviation from the initial timeline, the new approach meant the changes could be applied with minimal disruption. The revised shaft depth to 914 m was commissioned and hoisting of production ore was within three years of the start of construction. Cementation has a full Project Delivery System (PDS) to give a roadmap for successful project outcomes. Additionally, there is an Engineering Project Delivery System (EPDS) that is aligned with the overall PDS, but is specific to engineering processes and procedures. As can be seen, continuous improvement is a function of Cementation’s Internal Responsibility System for all areas of work including engineering, site construction, quality, environmental and, of course, health and safety. When everyone works safely, this is reflected in the project success and the schedule and budgets. With the shaft specific phases completed, Cementation has augmented its crew with civils contracting personnel given the highly specialised nature of some of the civils work being undertaken as part of the ore and waste handling systems to ensure early gains are not lost and the client’s production profile is maintained. Using rope guides, the hoisting rate of 8,000 t/d was achieved with 18 t skips travelling at 15 m/s from the mid-shaft loading pocket (914 m depth) and 10,000 t/d with skips travelling at 21 m/s from the shaft bottom location (1,500 m). This has surpassed the original design production rate. IM: What safety procedures has Cementation set up to enable work to continue even with social distancing measures in place? Cementation: Our projects have had various responses to the social distancing requirements, which has led to a change for some in the rotation schedule to reflect the currently understood incubation/asymptomatic carrier transmission schedule. For the current work at Young-Davidson, Cementation has brought in additional personnel carriers to enable distancing while travelling. Employees wear masks when travelling in vehicles as proper social distancing is challenging. Each worker at Young-Davidson for Cementation is issued with two masks every shift so they have options if social distancing is not possible. We have also instituted staggered start times and reduced the capacity of the cage for travelling, with a mask requirement for all personnel within the cage, to help with social distancing measures. IM: How is the project seen as representative of the company’s wider shaft sinking expertise? Cementation: For Cementation we have always enjoyed being involved at the early stages of projects to promote change and have the most opportunities to make optimisation suggestions A long section of the shaft sinking layout at Young-Davidson. that could be carried forwards. With our heritage in traditional shaft sinking and technically challenging projects, it should be noted that we are open to any and all innovations that do not compromise safety on our projects. Throughout our group we have been born from innovation in shaft sinking from our inception with the development and patenting of the ‘Cementation Process’ for sinking through difficult water bearing ground, which today the industry knows as cementitious grouting. It has been a natural evolution to add a wider variety of sinking options such as large diameter raiseboring, successfully, in hard-rock conditions. Our strong in-house engineering and engineering studies groups, supported by our contracting groups for constructability and safety, allow us to consider options for changing conditions and scenarios. This flexibility is further augmented by our approach to commercial and contractual arrangements. Oftentimes, this allows our approach to pivot with client requests, rather than be locked into rigid arrangements that cannot easily accommodate change. Cementation introduced target style alliance contracting into the North America mine contracting market, with the first active sinking project to utilise this approach being Falconbridge’s (now Glencore) Kidd Mine D #4 Shaft project. Another technically challenging project, a winze in an operating mine, which we proposed be worked on two separate sections to fast track the schedule, was then connected for the final design. The parallels to the legs approach at Young-Davidson and the similar benefits realised are apparent. IM: What aspects of this project will help the industry move forwards in terms of speeding up development rates, improving safety, lowering shaft sinking costs, lowering mining’s environmental footprint, etc? Cementation: Cementation takes care to consider all stakeholders and relationships; the project culture and morale can be as important as the technical expertise or contracting ability, all things being equal. As is the case at Young-Davidson, close integration between the owner and the contractor teams over the entire evolution of the scheme, with flexible engineering and planning being paramount, are key for successful collaboration and project success. Effective contractual and commercial formats that foster this attitude are vital to give the technical personnel the ability to adapt to changing conditions – in the ground or the markets – and deliver a successful project based upon criteria that may be fluid over time. Noting that shaft sinking is itself a specialisation, there are many subsets to that discipline and new options and approaches regularly arise, often organically as an enhancement or combination of existing techniques. Certainly the use of large diameter raiseboring elaborates upon earlier smaller borehole hoisting shafts, but, with advances in drilling technology and accuracy, the options for the application become wider. It should be noted there are four key points that should be addressed for successful large diameter raiseboring, especially for their incorporation into shaft projects such as this in an operating mine: n Is the size and length within current capabilities? Legs less than 1,000 m long and diameters less than 6.1 m; n Is the ground suitable? Sidewall stability and stand up times until ground support installed are a must. Are water inflows an issue for flows or destabilisation?; n Do you have access to the bottom of the pilot (for survey) and ream (for waste handling)? Necessary for installation of reamer head on drill down, ream up approach; and n Can you handle the waste underground? A 5.52 m ream may progress at 0.5 m/h, generating 12 cu.m of in-situ volume (or 40 t/h) of spoils that may have to be blended with other waste for system compatibility. Specifically at Young-Davidson, the opportunity of the MCM shaft for hoisting raisebore cuttings was an enabler for the project to take advantage of the large diameter raisebored shaft approach for a borehole hoisting shaft. IM SEPTEMBER 2020 | International Mining 79