IM 2020 September 20 | Page 80

HIGH PROFILE Full-face raiseboring was used by Cementation at the Young-Davidson shaft sinking project Full-face flexibility Cementation’s shaft sinking work at Young-Davidson flexed the contractor’s innovation muscles, with large diameter raiseboring in a three-leg (two phases) approach helping deliver the lower mine expansion. IM got to the bottom of this recently-completed project Project: Young-Davidson gold mine, Ontario, Canada Client: Alamos Gold Scope: Cementation has been involved in the Young-Davidson shaft project near Matachewan, in northern Ontario, for over 10 years. During that time it has provided studies, engineering, optimisation, construction and commissioning. The scope has encompassed deepening of the existing MCM rectangular shaft, a new Northgate production shaft, plus waste and ore handling infrastructure. Timeline: Work started in 2009 and the Northgate shaft was successfully commissioned earlier this year. IM: What innovations has the company employed to ensure it sticks to the budget and timeline set out by the client? Cementation: Early contractor involvement in a project allows the most impactful input to affect change for project estimates and schedules, as well as determining realistic and viable parameters with team buy-in throughout. This is especially true when, as in the case of Cementation, the contractor also fields a full disciplinary engineering group that can work with the operations team to provide robust solutions that work. In 2009, Cementation was invited to participate in a shaft trade-off analysis for the Young- Davidson project that would focus on two main shaft options for the new production shaft; the base case being a concrete lined shaft from surface as per the prefeasibility study and an alternative case of deepening the existing MCM shaft on the property, supplemented with a ventilation raise to support ongoing mining activities. The objective was to identify the optimum shaft option that would be incorporated into the feasibility study. The trade-off considered a raisebore or alimak pilots and slash or benching for the new 5.5 m diameter shaft excavation to 700 m depth, with provision for later deepening to the final 1,503 m planned shaft bottom. All three methods had the potential to achieve the final result, but the fullface raisebore and the Alimak pilot and bench had shorter schedules than the Alimak pilot and slash option. In addition, the full-face raisebore was substantially cheaper than the similar duration benching option, plus, when evaluated for the entire shaft length, the raisebore option required less lateral development than the mechanised raising methods. In September 2009, the decision was made to use the full-face raisebore option in two legs with upgrades to the existing MCM shaft for the feasibility study. In February 2010, Cementation was awarded the engineering, procurement and construction contract for the MCM shaft upgrades and the new Northgate shaft, together with headframe and hoisting plants. This approach allowed an integrated team familiar with the project to move through all of the project phases and, with Cementation’s in-house engineering capabilities and contractor knowledge for constructability and safety reviews, the designs were able to be continuously optimised. As the project moved into the detailed engineering phase, the team elected to proceed with a koepe hoist and a concrete rather than steel headframe, largely to reduce project capital costs. Friction hoists typically require less room and power than an equivalent drum hoist. In this instance, it was decided to tower mount the hoist within the headframe. Friction hoists are not ideal for traditional shaft sinking, but since the choice here was for a bored full-face shaft there was no requirement for a sinking excavation setup. Hoisting systems within a bored shaft require it to be bored to considerable accuracy to avoid time and capital costly re-work or modifications to fabricated designs to accommodate. To mitigate this risk, Cementation used the MICON selfsteering Rotary Vertical Drilling System (RVDS). After the pilot hole broke through for the first 460 m deep leg, the maximum deviation for the hole was 180 mm to the east, with a total deviation at the bottom of the hole of 40 mm northeast, well within the 300 mm acceptable deviation design parameters, so the estimate and schedule were protected. Typically concrete headframes are constructed by slipforming the concrete shell, then equipping the internal structure. The headframe contractor selected for the project by Cementation – Tesc out of Sudbury, Ontario – proposed a jump forming system that allowed the steel interior to be installed as the concrete exterior was being raised. Tesc and the Cementation engineering team worked to approve the approach. Beyond these immediate advantages, the new approach also allowed for a pause in the headframe construction to install the ground support in the first leg of the shaft below as we could not start piloting and reaming the second leg until this task was carried out. Slipforming the headframe would not have allowed for such a pause in headframe construction. During construction, the decision was made to temporarily shorten the depth of the production shaft and utilise a mid-shaft loading pocket for interim production hoisting. This allowed for earlier production and the third leg of the production shaft to 1,500 m was excavated under a pentice with eventual changeover to the shaft bottom loading pocket. Cementation’s approach allowed this option to be pursued without detrimental effects to the project economics, for production and capital purposes. Although this 78 International Mining | SEPTEMBER 2020