Specific water quality monitoring has been established at : 1 ) the Mt Wickham gully remediation site , 2 ) the Glen Bowen gully remediation site , 3 ) Strathbogie hillslope runoff diversions above the gully , 4 ) Mount Pleasant runoff management within a gully and 5 ) Havilah future gully remediation site .
The full vegetation and water quality monitoring results are reported in Section 4.3.1 , but Table 4 summarises the outcomes to date .
The results highlight significant improvements in several key indicators at two sites , in particular the Mt Wickham large scale gully remediation site which has shown significant improvements in land condition , vegetation cover , sediment loads and relative concentrations between the treatment and control sites . In addition this , the large scale sites also reveals important learnings for other investments within the LDC Project and for future work both within the LDC Project and for similar management interventions undertaken elsewhere .
35