SECTION 1 - INSTALLATION
Installing Wall Cabinets
Illustrated Method Sheet 104
Step 1
Prep and Place the First Wall Cabinet
1.1
Confi rm that
Wall Cabinet doors and
shelves are removed
from the cabinet box
and neatly stored out of
the way.
Stage the stripped
Wall Cabinet boxes to
the areas they will be
installed.
1.2
Identify the location on
the wall where the edge of the
fi rst Wall Cabinet will lie.
The process in this
Illustrated Method
Sheet assumes that the
steps described in the
previous documents
have been completed.
If there are no tall cabinets in the
installation, start with the center
most full height wall cabinet on
the most complex wall.
See IMS #102 for help in de-
termining the best starting point
and proper layout.
The proper conditions for
this to take place are:
Tools are laid out, the
cabinets have been
unwrapped and
inventoried, studs have
been located and the
Base and Wall Cabinet
Index Lines have been
determined and marked
on the walls.
In addition, any tall cabi-
nets are properly secured
in their positions.
©2017 PCS Professional Cabinet Solutions. All Rights Reserved.
1.3
Measure back
from that point to the
nearest stud location.
Subtract 5/8” (the thick-
ness of a side panel)
from the dimension and
transfer that mark to the
cabinet’s inside back.
Section 1: IMS 104