EFERT Connect 1H 2018 Magazine | Page 18

ESD Replacement Project Enven was commissioned with Honeywell Integrated Control System. This integration of DCS and ESD had its pros such as unified HMI but there were massive reliability issues ranging from ESD card failures to dependence of ESD on the DCS and Ethernet network for safety and control actions. Keeping in view these issues, it was decided to replace Honeywell’s ESD: Safety Manager with more reliable, robust and state of the art Schneider Electric’s ESD: Triconex. Plant-2 ESD Replacement Project was one of the most challenging projects I&E has ever executed be it the criticality, the technicality or the high stakes involved. ESD Project was first ever I&E project to be on the critical path of the turnaround. The commissioning took place in the limited window of TA-18. It was a humongous task to shift more than 3000 hardwired loops, test each loop, simulate and test 150 plus interlocks and test each of the 325 HMIs in this short span of mere 21 days. Focused efforts and detailed working in the pre-commissioning and commission phase made it possible to have a flawless execution. The project team comprised of Asad Naeem, Mohsin Mukhtar Khan, Muhammad Hamza Khan, Khalid Bashir Awan, Muhammad Kamran Shamim and Muhammad Faizan Arshad Ch from Instrumentation, Ishfaq Javed from Electrical, Muhammad Zaheer Abbas and Arsalan Tahir from Operations and Safi Ullah Khan and Adnan Ali from Process. Muhammad Faizan Arshad Ch Workshop highlights