CRITERIA FOR QUALIFICATION Three points of credit are available for completing the following:
� Include building enclosure, flashing, and material installation details in plans and specifications. � Complete field testing of the building enclosure to verify performance for air infiltration and water management. A mock-up of the wall assembly must be tested according to industry standards.
VERIFICATION
Documentation: The Rater will collect a report from a responsible professional indicating that specified materials were used, the materials were installed as specified, and the mock-up passed the building enclosure testing.
INTENT
To ensure proper installation practices for the building enclosure to improve durability and water management.