Receive final inspection from the Secretariat for Urban Development and Ecology
Agency : Secretariat for Urban Development and Ecology
A final inspection is carried out to verify that the warehouse has been built in accordance with the
regulations and the approved plans. The inspection is scheduled at the time of the notification of
the completion of the construction.
1 day no charge
3 days MXN 282
The procedure is legislated in Art. 351 of the Urban Development Law of the State of Nuevo Leon.
13
Obtain certificate of completion of construction work from the Secretariat for Urban
Development and Ecology
Agency : Secretariat for Urban Development and Ecology
Once the final report is revised and the appropriate fees are paid, the Secretariat for Urban
Development and Ecology will issue the certificate of completion, certifying that the warehouse is
built in accordance with existing regulations and approved plans.
The procedure is legislated in Art. 123 of the Building Code of the City of Monterrey, Nuevo León.
The basis of the cost is in Art. 52-BIS, Section VIII of the Finance Act for the Municipalities of
Nuevo León.
-For the issuance of various certificates and certifications: 3.5*daily minimun wage (Unidad de
Medida de Actualizacion-UMA)
Takes place simultaneously with previous procedure.