Doing Business 2020
9
Mexico
Obtain excavation permit from the Secretariat of Public Services (Technical Department,
Permit Coordination)
Agency : Secretariat of Public Services (Technical Department, Permit Coordination)
This permit allows BuildCo to conduct any excavation of the road to install the pipes. The
pavement must be repaired to its initial status after the completion of the work.
5 days MXN 84,630
21 days MXN 29,084
1 day no charge
To obtain the permit, BuildCo must submit:
a. Communication addressed to the Technical Director;
b. Proof of payment of property tax;
c. Copy of the constitution;
d. Official identification of the legal representative;
e. Work project;
f. Work program;
g. Copy of professional license and identification of the DRO;
h. Payment of fees;
i. Escrow;
j. Feasibility of water and drainage.
The fee for this procedure is:
-Permit for the underground introduction of any type of drivers for goods of common use (water):
7*daily minimun wage (Unidad de Medida de Actualizacion-UMA)
-Multiplied by linear meters to the main network: *150
10
Request and connect to water and drainage services at the Water and Drainage Services of
Monterrey (SADM)
Agency : Water and Drainage Services of Monterrey (SADM)
BuildCo must submit the following:
a. Document proving ownership;
b. Official identification of the legal representative;
c. Articles of incorporation;
d. Land use permit;
e. Building permit;
f. Registration of wastewater discharge;
g. Architectural plan.
The procedure is legislated in Art. 42 of the Finance Act for the Municipalities of Nuevo Leon and
Art. 31 of the Building Code of the City of Monterrey, Nuevo León. The basis of the cost is in the
Second Agreement, Title Services Water and Sewerage of Monterrey, IPD Meter Installation Fees
for Connection and Service Standards Reinstalling Meter; Official Gazette no. 147.
The fee for this procedure is:
-For the infrastructure contribution: MXN 8,844.2
-For water connection: MXN 9,140
-For drain connection: MXN 9,350
-For the meter and installation: MXN 1,750
It is assumed that the average water need is 662 liters/day and the average wastewater flow is
568 liters/day. A diameter of 1 inch for the drinking water connection and 4 inches for the drain
connection are also assumed. Connection costs include labor, materials and costs of repaving.
11
Submit completion of construction work report (oficio de obra terminada) and request
stamp by the Secretariat for Urban Development and Ecology
Agency : Secretariat for Urban Development and Ecology
BuildCo or the Responsible of Construction works (Responsable de Obra) must provide a final
report to the Secretariat for Urban Development and Ecology which certifies that the construction
work was executed under his supervision, complying with the rules and following what was
authorized.
BuildCo or the Responsible of Construction Works must submit the following:
a. Application form;
b. Proof of payment of property tax;
c. Responsive letter and copy of the professional license of the DRO;
d. 2 original and 1 copy of the flat plane of history;
e. Approval of civil protection;
f. Articles of incorporation.
g. Approved building license
Payment is then made to obtain the stamp.
The procedure is legislated in Art. 123 of the Building Code the City of Monterrey, Nuevo León.
Moreover the obligations corresponding to the "Responsable de Obra" can be found in Art. 12 of
the Building Code
Page 27