Connect Arlington - TAC Report September 2017 Connect Arlington - TAC Report September 2017 | Page 9

CORRIDOR 4 I-30 Corridor
CORRIDOR 5 IH 20 Corridor
CORRIDOR 6 Pioneer Parkway – Highway 303

Corridor Recommendations

CORRIDOR 4 I-30 Corridor

Desired Service Characteristics »»
Regional connections
»» Express service
»» Commuter service
»» Comfort
»» Amenities
»»
Serves commuters to Fort Worth and Dallas , as well as visitors
Mid-term Recommendations »»
To better move citizens and visitors along Interstate 30 , the Committee recommends the implementation of a Bus Rapid Transit or High-Intensity Bus Service .
Long-term Recommendations »»
The Committee supports High Speed Rail in this Corridor as a long-term solution , if the region is able to complete such a project . If High Speed Rail is not constructed in the Corridor , the Committee recommends Bus Rapid Transit or High Intensity Bus service .

CORRIDOR 5 IH 20 Corridor

Desired Service Characteristics »»
Regional Connections
»» Express Service
»» Commuter Service
»» Comfort
»» Amenities
»»
Serves commuters and residents Mid-term and Long-term Recommendations
»»
To better move citizens and visitors along Interstate 20 , the Committee recommends the implementation of a Bus Rapid Transit or High-Intensity Bus Service in this Corridor , as both a midterm and long-term recommendation .

CORRIDOR 6 Pioneer Parkway – Highway 303

Desired Service Characteristics »»
Fixed-route Service
»» Provides link to neighboring cities
»» Serves as a reliever for I-30 and I-20
»»
Serves residents , businesses , seniors , tourists , and shoppers
9
Mid-term Recommendations »»
Provide Demand-Response Rideshare service within Corridor 6 .
Long-term Recommendations »»
Corridor 6 will be best served by fixedroute service , such as autonomous , rubbertired shuttles , or Personal Rapid Transit . Any service along this Corridor should be elevated to prevent increased traffic congestion .