High-volume fresh air retrofit improves comfort in FMCG factory.
PROJECT
INCORPORATING COLD CHAIN
Bespoke high-volume cooling system transforms conditions in
All images by © Cold Link Africa
FMCG production facility
Technical detail supplied by Zuber Suleman BSc Eng S Projects
High-volume fresh air retrofit improves comfort in FMCG factory.
Retrofitting a cooling system into a live FMCG manufacturing environment is seldom straightforward. In this case, the challenge was compounded by high internal heat loads, strict operational constraints and an unusually tight installation window. Yet through a combination of detailed engineering, close collaboration and carefully selected equipment, the project team delivered a high-volume, energy-efficient ventilation system that has significantly improved working conditions while maintaining cost discipline.
At the heart of the project was a simple but pressing problem: the factory floor was too hot and too humid. Much of the heat load originated from heated shrink-wrap tunnels used in the packaging process – essentially large electric heating elements operating continuously. These, combined with processrelated moisture, created an uncomfortable environment for staff and placed pressure on operational performance.
Rather than pursuing a conventional full mechanical cooling solution, the design team focused on a more nuanced approach. The client’ s brief was to improve comfort conditions in the most cost-effective way possible, both in terms of capital expenditure and longterm operating costs. This required a system that could respond dynamically to ambient conditions, minimise energy use and integrate seamlessly into an existing building not originally designed for such infrastructure.
The project officially commenced on site in late October 2025, following approximately a year of design development, simulations and cost optimisation. Commissioning was achieved by the end of March 2026, with final completion in April. However, the most critical phase of the installation took place during a narrow shutdown window between 12 December 2025 and 6 January 2026. During this period, the factory halted production, allowing the contractor to carry
Overview of the rooftop installation showing the bespoke air handling units, ductwork and associated mechanical plant.