Clearwater County Highlights October/November | Page 13

NOV. 2016 | 13 Service Level Summary Each year, Council reviews the service level needs and wants of the community in a variety of manners - talking with committees, businesses, residents and industry - in order to set appropriate service levels for the community as a whole. Service level decisions provide administration direction for budget Capital Budget A capital budget includes estimated expenditures needed to pay for assets such as land, building construction, roads, bridges and other major permanent improvements or equipment. A capital item has a life expectancy of more than one year, and in Clearwater County the capital budget is based on a 10 year plan. The following headings represent asset management strategies that plan for replacement of capital items. Public Works ASPHALT OVERLAY Maintains the integrity of existing paved roads (approximately 350kms) and the asphalt replacement plan operates on a 15 year cycle. Each year this program overlays approximately 22 kilometres of surfaced road. ⇒⇒ Total annual budget approximately $5 million. GRAVEL ROAD REHABILITATION Addresses the upgrade of gravel roads (approximately 1900 kms) on a schedule based on various factors including the condition of the road, traffic volumes and utilization. Rebuild or re-conditions approximately 32 kilometres of road each year. ⇒⇒ Total annual budget approximately $4.8 million. preparation. Many of the capital and operating budget amounts reflected in this summary document state the usual annual expenditures associated with providing the County’s current programs or services. It is important to note that Council reviews, deliberates and NORDEGG CAPITAL Includes road infrastructure costs within the hamlet. ⇒⇒ Total budget varies from year to year based on Council’s approved projects. ⇒⇒ No budget allocated in 2016 ⇒⇒ Nordegg Commercial Core servicing and road improvements, budget estimate $3 million in 2017. BRIDGE REHABILITATION Previously, the Province partially funded bridge rehabilitation. With no provincial funding for the past five years, Council chose to fund rehabilitation of some of the County’s 175 bridge structures, in an effort to minimize restrictions or closures. ⇒⇒ Total annual budget approximately $3.6 million. ⇒⇒ 3 major bridge projects and 4 bridge sized culverts scheduled to be replaced in 2017. GENERAL CAPITAL Includes heavy equipment purchases, based on varying life-cycles/asset management best practices. ⇒⇒ Total annual budget of approximately $900,000.00. BASE PAVE & RESOURCE ROADS Includes any new surfaced road projects - not an annual program, budgeted for on a project specific basis. ⇒⇒ Range Road 8-0 improvements, budget estimate $950,000.00 in 2017. approves both the operating and capital budgets annually, and has the sole discretion to add, amend or remove items from budget. During budget deliberations, Council looks at their long-term planning and determines how operating and capital expenditures are funded - reserves, current tax dollars or debentures. ISOLATED SITELINE IMPROVEMENT Includes enhancement of visibility at intersections. ⇒⇒ Total annual budget approximately $100,000.00. Any questions? Please call 403-845-4444 to have your inquiry directed to the appropriate department. FACILITIES Includes land, engineering and development of County buildings and lands - current projects: Caroline land development salt/ sand storage facility and light industrial lots and County’s north development salt/sand storage facility and proposed operations and administration building. ⇒⇒ The total budget varies from year to year, based on Council’s approved projects. ⇒⇒ Total budget of approximately $15 million in 2016 and $11.7 million in 2017. WASTEWATER Reflects scheduled replacement of sewer lines or infrastructure. ⇒⇒ The total budget varies from ⇒⇒ year to year, based on Council’s approved projects. ⇒⇒ Total budget of approximately $1.7 million in 2017, upgrades to Condor lift station and lagoon. ACCESS ROAD Includes undeveloped road allowance development, on a cost-share basis with developers wishing access to private land. ⇒⇒ Total annual budget approximately $150,000.00. www.clearwatercounty.ca