British Water Members' Handbook 2017 2017 Edition | Page 59

In 2012, main contractors MVB approached Asset International Limited and Uponor Project Services to examine the complex design of the Lee Tunnel twin culvert pipeline outfall. The Asset/Uponor designed twin culvert pipeline outfall project was divided into a land section, which was installed by MVB and a marine section, which was installed by marine contractor, Commercial Marine & Piling Ltd (CMP) alongside Uponor. The Asset and Uponor PS partnership set about using their combined design expertise for land and marine applications to re-engineer the project by creating a landmark design - the biggest plastic outfall ever installed in UK and one of the biggest in terms of diameter worldwide. The proposal to overcome this enormous challenge; inclusive of 880 metres of 3000mm diameter Weholite pipes laid as a twin culvert along with twelve large-scale Weholite Modular HDPE boxes; also the provision of installation, supervision, site services and health and safety management. The project was divided into a land section comprising of 105m of twin culvert laid at 10m depths. This section had the added complication of needing to break through the tidal protection wall that stops the Thames flooding Europe’s largest treatment works at Beckton. This issue was overcome by utilising a giant 7m x 11m x 5m Weholite Modular box to house a 3000mm spool section to complete the installation. The operation to install the remaining 335 metres of twin culvert section into the River Thames was carried out by marine contractor CMP, alongside the Asset and Uponor PS partnership. This ambitious marine project was complicated still further by the fact the pipes needed to be submerged under an existing jetty structure and sections of the project were often isolated by the tide (which in the Thames have a rise and fall of up to 7 metres), with no access from land. All the Weholite pipes and modular boxes were manufactured and prefabricated at Asset’s south Wales factory. The pipes were then delivered to site in 18 metre lengths, where they were welded into strings of up to 90 metres. The 50 tonne strings were then lifted onto the water using three mobile cranes in tandem and prepared for towing to the submersion site, located around 3km up river. Part of this preparation involved utilising Uponor’s patented grouting process which eliminates the need for heavy concrete collars to ballast the strings. This traditional way of installing marine pipelines can often be extremely risky during submersion. Filling the hollow Weholite profile with an inexpensive and pumpable grout is much safer and affords for a much quicker preparation time. With no concrete collars a smaller trench is needed, the dredging operation is minimised and the volume of excavation is therefore drastically reduced. Since submarine excavations are more expensive than on dry land the advantages of Weholite are transparent. By using the grouting system, Weholite submersion is much easier to control and ultimately safer. Once the pipe strings were ready, they were towed individually up river by tugboat and then submerged. Specialist divers were used to bolt up the innovatively designed quick connect flanges that joined each pipe string. The project also included installation of over 11,000 m2 of steel sheet piling to allow the dredging of the river bed so the pipes could be laid free from obstruction. Over 28,000 m3 of riverbed materials were dredged and much of the dredged materials were reused to backfill the pipes once installed. This provided an environmental advantage by vastly reducing the amount of materials to be taken off site, thereby saving on the carbon footprint. Emmanuel Costes, construction manager at MVB, commented: “We were very happy with the Weholite technology employed in the implementation of the Lee Tunnel Outfall pipeline. The specifications of the project were very particular, however the solutions provided by the Asset International/Uponor collaboration were impressive, ticking all of the boxes that this complex, and in many cases unique, project demanded.” The scale and scope of the installation means that not only has it become the UK’s largest plastic outfall pipeline, but it also represented the UKs first ever sub-sea installation of a sectional installed multi-directional sewage pipeline. For more information about Weholite call Asset International Ltd 01633 273081 or visit www.weholite.co.uk 01633 01633 273 273 081 081