Architect and Builder September 2020 | Page 45

SECTION viability study, various financial institutions were approached. Agreement with Nedbank was reached and they were a pleasure to work with. With regards the sale process - in order to release the funding a pre-sale threshhold was set at 80% of the total sales value of the units. As it turned out the development was sold out in under a month which allowed construction to commence earlier than expected. The construction process started off slowly with the main challenge being the co-ordination between the demolition of the existing building whilst maintaining the lateral support integrity of the existing basement and the installation of the foundation piling. Thanks to Ross Demolition, Franki and JLK Construction for their assistance in solving these challenges. Once out of the ground construction proceeded apace despite the best efforts of the neighbours from the legal fraternity who continually threatened to interdict the developers for excessive noise and disturbance. This problem had been anticipated and at the start the developers set up a liaison committee with two members of the Cape Bar Council. Consensus was reached with an agreement on working hours and the implementation of noise reducing measures on site. As a result this was the quietest site the team had ever experienced. As a consequence of the limited working hours the construction period was extended by some 3 months which had an effect on the overall development cost of the project. However, when all was said and done the projected return on investment was maintained with each shareholder achieving an excellent annualised return on capital. Thanks go to all involved for the extremely positive working environment which is reflected in the iconic end product. 8TH FLOOR TYPICAL FLOOR GROUND FLOOR Tuynhuys 45