Architect and Builder Retail Retrospective | Page 160

company entered into a 75 / 25 joint venture with Dlamini Construction .
“ While this was a client requirement on the project , it is also in line with Murray & Roberts ’ strategy of bringing emerging contractors into the economy ,” Neethling says .
The scope of work comprised all construction as well as the finishing of the public areas and
those of three of the major anchor tenants . External works included the receiving yards which measured a further 10,000m 2 of paved and / or concrete surface beds , parking for 3,000 vehicles and general paving and landscaping .
When completed , it was approximately 55,000m 2 and housed four anchor tenants and 118 line shops linked by malls with exclusive finishes .
160 Vaal Mall