Architect and Builder August 2016 | Page 55

right contractor, to meet the project’s specific requirements. This resulted in the appointment of a specialist waterproofing consultancy. With a new contractor and a new specification in hand, the waterproofing works commenced again in all earnest, following the re-installation of the acrylics. The new product installation did not go without its own inherent problems, as the application method had to be changed from spray-on as advised by the product supplier (but which proved impossible), to roll on, having a further knock-on effect on both cost and time. Project Close In view of the above, the tank completion was delayed by almost 18 months and was successfully opened to the public in June 2016. ARCHITECTURE & STRUCTURE The new I&J Ocean Exhibit is a 20x12m reinforced concrete rectangular tank with chamfered corners. The concrete walls provide support to the adjoining first floor and roof slabs. The floor of the tank is a reinforced mass concrete raft founded on the Two Oceans Aquarium in-situ rock. The floor varies from 550mm to 400mm thick and was cast as a continuous pour with no construction joints. The main tank concrete wall panels were poured in single continuous 8m high lifts to avoid horizontal construction joints. To make this possible, pull-out bars were used for the adjoining slabs, together with mechanical couplers for the adjoining beams. PVC waterstops anchored into the floor slab were used between adjacent wall panels. Formwork for the tank walls was kept in place for a minimum of 7 days as part of a stringent curing regime. Concrete with a corex-slag replacement of 50% was specified for the tank structure to increase marine-classification durability. Additionally, the concrete was waterproofed with a specialist elastomeric polyurea lining to meet a completely water-tight specification. Specialist rebates were provided to the acrylic windows and tunnel roof to accommodate the stringent tolerances required by the acrylic installer. In most cases, specialist form rebates were constructed off site to mimic the acrylics, and installed within the formwork. BELOW: NORTH ELEVATION 53