Architect and Builder August 2016 | Page 54

and installation of the Acrylic ‘windows’, which not only had a long lead time, but had been the subject of an extensive international pre-contract assessment. After numerous rounds of pricing and due diligence on quality, an Italian firm, Clax Italia srl, was appointed. Conventional JBCC contracts, guarantees and the like all had to be translated into Italian prior to si gnature. The tank further had to be constructed in such a manner, and to exact tolerances, so as to minimise construction joints and to allow not only a perfect fit for the acrylic panels, but to also facilitate water tightness in order to achieve an acceptable finish for waterproofing. The co-ordination of the tank design and construction between the client, engineers, main contractor, waterproofing specialists and the acrylic supplier (who undertook his own installation), was key to success of the tank construction. Apart from the requirements of the tank, the project entailed the provision of new filtration plant rooms, workshops and ‘back of house’ facilities for the TOAT portion of the project for fit out by TOAT staff. A further aspect of the development was the construction, within the aquarium extension, of an independently operated events space, and facilities, that overlook the main acrylic window. GROUND FLOOR PLAN FIRST FLOOR PLAN KEY TO PLANS 1 OCEAN EXHIBIT TANK 2 TUNNEL 3 DOUBLE VOLUME 4 EXHIBITION SPACE 5 LIFE SUPPORT 6 OFFICES 7 STAFF 8 CHEMICAL STORE RIGHT: SECTION AA BELOW: SECTION BB 52 9 REFUSE ROOM 10 DELIVERIES 11 DELIVERY AREA 12 WORKSHOP 13 TOILETS 14 CONFERENCE LOBBY 15 CONFERENCE ROOM 16 PLANT ROOM 17 STORE 18 PUMP ROOM 19 EXISTING AQUARIUM 20 OCEAN 21 ONE & ONLY HOTEL 22 DOCK ROAD 23 KITCHEN 24 ROOF DECK 25 EXISTING BUILDING 26 DIVING POOL 27 FEEDING / MEDICAL POOL 28 COVERED WALKWAY PROJECT CHALLENGES Excavation in Rock It had been noted, during the geotechnical investigation, that the underlying bedrock would require drilling and blasting below 1.5m. This was, however, not a concern until such time it was realised through design review and the identification of servitude access constraints raised by the V&AW and the adjacent One & Only Hotel that the storm water line needed to be rerouted. This entailed excavating in hard rock for almost 50m. At that point, blasting was no longer feasible due to the advanced status of the structural work and excavation continued by pneumatic means and local shot blasting only. This had a dramatic impact on the structural time line and constrained the tank construction works. Acrylic Removal and Waterproofing The tank concrete was tested for water tightness before the overall waterproof liner was installed, but waterproofing membranes were installed locally to the reveals so as to seal the acrylic panels to the membranes. This, unfortunately, led to water ingress behind these membranes due to water pressure. This resulted in the Italian team having to be mobilised and the acrylics having to be removed again to effect repair of the waterproofing membranes. During this time, the specification of the waterproofing was re-considered. An extensive review period followed to identify not only the right product, but also the Two Oceans Aquarium