Apparel Online Bangladesh Magazine May Issue 2019 | Page 53

are suggested by the buyer, and the other with more number of in-between micro activities (in-house activities) to exercise control over macro activities. To decide upon which all activities should be there in TNA calendar, one must prepare either PERT network or Gantt chart mandatorily and the resultant critical path should be the activity chain for TNA calendar, all activities falling in critical path are critical activities. Critical activities should always be on focus, a single minute delay in any of the critical activities may lead to final shipment delay. In case some of the buyer- suggested milestone activities are part of the critical activities, then well and good; other non- critical activities will have slag time anyway. Critical activities in any TNA remain unchanged throughout order execution process WRONG Generally TNA is prepared as proposed plan of execution. The planned duration and sequence of activities decide the critical path. However, during actual execution of order, duration of any activity may stretch beyond planned duration, which may change the critical path. If duration of any non-critical activity extends beyond the slag time, then that particular activity may become critical and critical path will change accordingly. This phenomenon happens frequently during order execution and therefore specialised software is necessary for tracking TNA which automatically and dynamically changes the critical path during order execution process. Manpower resource dependency is not so important in preparing critical path or TNA WRONG It is a common practice to estimate the duration of activities in days or hours rather than in ‘man-days’ or ‘man-hours’. In the given four task example assignments, both B and C can work concurrently as per dependencies concerned. However, if same manpower is to be used for both B and C, the dependency relation will change accordingly and B and C will become sequential processes. Linear activity sequence In a typical scenario, one order may have 40-50 activities to be tracked/ followed up/managed (from order receipt to delivery) by 5/6 people, which obviously means one resource person is responsible for more than one activity. Therefore, resource dependency is very important in TNA. Different orders should be followed up using separate TNA Parallel activity sequence as PERT network WRONG It is a common practice to have one merchandiser responsible for multiple orders. Prevalent practice is to prepare separate TNA for different orders and track in isolation. Since resource utilisation for more than one order is not synchronised, and since it is calculated separately, situations will arise when same resource is expected to work on more than one place, which is impossible. Therefore, when common resource is to be used for multiple tasks, it is logical to combine all TNAs into one integrated to avoid confusion of priorities. Spreadsheet software is enough to manage TNA WRONG It was found that majority of the organisations use spreadsheet (e.g., MS Excel) to schedule activities against target date, which they call TNA or critical path. With full potential of spreadsheet being used, all requirements of TNA still cannot be managed. Firstly, existing use of spreadsheet is merely typing activities and dates in tabular form. Hardly anyone uses formula, macros or conditional formatting of spreadsheet to calculate variations and get alarms. Therefore, the purpose of using spreadsheet is virtually defeated. Secondly, spreadsheet cannot To decide upon which all activities should be there in TNA calendar, one must prepare either PERT network or Gantt chart mandatorily and the resultant critical path should be the activity chain for TNA calendar, all activities falling in critical path are critical activities. Critical activities should always be on focus, a single minute delay in any of the critical activities may lead to final shipment delay. generate automatic Gantt chart or calculate critical path and many other requirements that are necessary for managing TNA. Spreadsheet when used cleverly can generate linear calendar dates, calculate variance between planned and actual completion date and raise visual alarms. Specialised softwares are required to manage TNA RIGHT Managing TNA requires automatic Gantt chart preparation, automatic critical path preparation, automatic resource utilisation calculation, automatic integration of more than two Gantt charts with resource constraints automatically reflected, different options of task relationships like start-start, finish-finish, as well should be able to change all synchronised activities during any change of plan during progress of the order. Further, the software should help or guide the user with several visual/colourful benchmarks and alarm systems. Generally specialised project management software is capable of providing maximum of these features, thus ideal for managing TNA. www.apparelresources.com | MAY 2019 | Apparel Online Bangladesh 53